Newhaven Tram project update

(adapted form an email from ‘Trams to Newhaven’)

Leith Walk Planters

In order to facilitate construction of Trams to Newhaven project, the 14 planters that are currently situated on Leith Walk will be moved to the Leith Links / Duke Street / Lochend Road / Easter Road junction. This will be a permanent move in order to accommodate dedicated cycling lanes post construction. The planters will be moved as part of the enabling works commencing on Monday 18 November 2019.

We are aware that some businesses / residents have been looking after the planters and where this is known we have made contact to explain. An example of this is the Kadampa Meditation Centre who we visited to explain what is happening and to thank them for the work they have done. We will be attaching posters to the planters this week to highlight the planters being moved.

Trimming of trees at South Leith Parish Church Wall

In order to begin works on the South Leith Parish Church wall later in December 2019, TD Tree and Land Services Limited, a specialist in tree maintenance, will trim back overhanging branches in order to gain access to the wall. The works will take place over two days (Monday 18 and Tuesday 19 November) and will not damage the trees in any way.

Wherever possible all work will be carried out from the ground.  If required, trees will be climbed by trained personnel and will only take place once an assessment has been made that is safe to do so.

An eco-check for bats and nesting birds was undertaken recently which identified the trees had not been used by either species.

We will be highlighting both of above on the project website and in the electronic newsletter this week.

Constitution Street tram-construction start

(adapted from an email from the Trams to Newhaven project. Constitution St is not in LCCC’s area, but LCCC residents and businesses may wish to know the following.)

The Tram to Newhaven project team is hosting a drop-in event on Thursday 7 November from 12pm – 7.30pm at South Leith Parish Church where residents and businesses can come and meet the team who can answer any queries they might have about the planned works.

The first phase of work to take trams to Newhaven will start on Constitution Street on 18 November 2019. Continue reading