Leith Programme Stakeholder Update 111 – Phase 4 (Iona Street to Brunswick Street)

(adapted from an email sent by Michael Motion, Senior Project Manager, Infrastructure, Turner & Townsend at 17:08 on 2017_09_22)

Completion of the road surfacing works will be noticeable as we complete areas and move the major worksites southwards towards McDonald Road and Brunswick Street. With that being the case, we will now be closing both McDonald Road and Brunswick Street junctions on Wednesday morning, 27th September with local diversions put in place. This will coincide with the opening up of both Iona Street and Albert Street. McDonald Road and Brunswick Street will remain closed until completion of all works by the end of October, as will Brunswick Road where the site compound is located. Continue reading

Leith Programme Stakeholder Update 109: Phase 4 (Iona Street to Brunswick Street)

(adapted from an email sent by Michael Motion of Turner & Townsend at 14:51 on 8 September. )

Dear Stakeholder

Our contractor, Crummock, returned to site as of Monday 4th September to remobilise for the completion of the Phase 4 scope of works. At that time, Brunswick Road was closed to accommodate the site compound, and will remain so until the works are completed. Iona Street was also closed to allow commencement of works to realign the kerb line, commence the road surfacing works including the raised table construction and to complete the pavement slabbing. It is likely this will take up to 3 weeks to complete, during which time Iona Street will remain closed.

In addition to the above, we are also working in the following areas:

  • Brunswick Street junction to complete the remain footpath slabbing to the S/E corner
  • Croall Place to complete the remaining Scottish Water rectification works, and to resolve surface water drainage issues
  • 2 nr road crossings on Leith Walk, north and south of Albert Street.

Continue reading

Leith Programme Stakeholder Update 107: Phase 4 (Iona Street to Brunswick Street)

 (adapted from an email from Michael Motion, Senior Project Manager at Turner & Townsend, sent at 16:51 on 21 August 2017)

As of Monday 4th September, following the Edinburgh festival embargo, our Contractor, Crummock, will be returning to Leith Walk to complete Phase 4 of the Leith Programme.  We anticipate completing these works by Friday 3rd November (being an 8 week construction programme).  Continue reading

Leith Programme Stakeholder Update 105: Phase 4 (Pilrig Street to McDonald Road) – Weekly lookahead (w/c Monday 31st July 2017)

(adapted from an email sent by Steven Jackson, Associate Director, Infrastructure, Turner & Townsend, at 11:25 on 2017_07_28)

Following work completed to date we are targeting completing all pre embargo works and removing traffic management on Monday 31st July. Continue reading