Community Councils Together on Trams/Trams Team meeting, 25 June 2020

Minutes of the Community Councils Together on Trams/Trams Team meeting
(Construction Phase) via Google Meet on Thursday 25 June 2020 at 5:30pm Continue reading

Trams to Newhaven newsletter, 19 June 2020

Unfortunately, the newsletter was not published with a link to a version viewable in a browser. LCCC has replicated the text and links in the newsletter, for the information of its online followers.
Continue reading

Main construction start – Trams to Newhaven

(Copied from an email from Trams to Newhaven)

The main construction works for the Edinburgh’s Trams to Newhaven project will start from Monday 15 June 2020 in line with the Scottish Government’s Phase 2 ‘soft start to site works (only where physical distancing can be maintained).

Work on the project was stopped at the end of March to comply with Government guidance and to protect the safety of workers and residents during the coronavirus outbreak.

Following the First Minister’s announcement on 21 May of a phased return for construction sites, plans have been drawn up in line with Scottish Government safety guidelines and industry best practice to ensure the safety of workers and the public. At the briefing on 28 May the First Minister confirmed that site preparation could begin and, following the announcement today, main construction works can now start. This will encompass the existing sites on Lindsay Road, Melrose Drive and Constitution Street which will start from Monday 15 June. In addition, main construction works on Leith Walk from Elm Row to Crown Place will start on Monday 22 June.

In advance of this some preparatory works on Leith Walk will start on Monday 15 June 2020 ahead of the installation of traffic management which will begin on the evening of Friday 19 June and be operational from 5am on Saturday 20 June 2020 including Lothian Bus diversions. All traffic management arrangements are made in consultation with key partners in the city, including blue light services and public transport providers, through the Traffic Management Review Panel and are continuously monitored and reviewed to ensure they work as effectively as possible.

All works will be carried out through physical distancing and additional measures to protect workers’ health will include daily briefings, continuous on-site inspections and health and safety ‘ambassadors.’ The numbers of workers on-site will be kept to a minimum and a large proportion of the project office staff will continue to work from home. While physical distancing will be a key principle of construction working, workers will also have access to personal protection equipment (PPE) which they may choose to wear as an additional precaution if they wish. It should be noted that it may take time for the sites to become fully operational.

The logistic hubs at the Mitchell Street, Foot of the Walk, Dalmeny Street, Albert Street and Montgomery Street will re-open on Monday 22 June to support local businesses with deliveries and despatches. All communal bins that are currently situated on Leith Walk will be moved to the side streets.

If you have any queries please do not hesitate to get in contact.

Chris Wilson

For information

The Scottish Government’s phased approach to construction details six key phases to ensure work is carried out in a safe way. These are:

  • Phase 0: Planning
  • Phase 1: Covid-19 Pre-start Site preparation
  • Phase 2: ‘Soft start’ to site works (only where physical distancing can be maintained)
  • Phase 3: Steady state operation (only where physical distancing can be maintained)
  • Phase 4: Steady state operation (where physical distancing can be maintained and/or with PPE use)
  • Phase 5: Increasing density/productivity with experience

Public utility works: Leith Area

(adapted from an email from Graham Hall (CEC Senior Transport Team Leader) to Leith ward and Leith Walk ward councillors; with thanks to the councillor that forwarded it to community councils. Unfortunately, this only reached LCCC’s webmaster today [19 July].)

As you will be no doubt aware, The City of Edinburgh Council is carrying out significant pre-tram surfacing works in wards 12 and 13 at the current time via our Transport Design and Delivery section who have McLay’s Ltd carrying out numerous projects in preparation for the Tram extension works which are due to commence later this year.

In addition to these works City Fibre have started their programme to install fibre to the home in the area as well as the other utility providers continuing their business as usual.

It has been agreed with the CEC project manager (Steven Blacklaw) that the locality will coordinate these works around his significant programme to avoid conflict with different sets of work. As McLays Ltd are based in Airdrie and traditionally close down for the Glasgow Fayre fortnight commencing on the 12th of July I have delayed various utility works commencing until McLay’s have closed their sites down and to prevent additional pressure on the road network. The works below have been approved for the period 14th July 2019 to 30 July 2019 to avoid any conflict with the CEC programme.

Whilst there will no doubt be some form of delay caused by the various works, please be assured that every effort has been made to minimise disruption utilising the quieter school holiday period whilst still ensuring these works are completed before CEC’s contractor returns to recommence his programme. Please also note that where required, any works which may present significant disruption have been discussed and approved at the City Wide Traffic Management Group to ensure the most effective traffic management is employed.

Should you have any further questions please do not hesitate to call on the number below.

Utility Location Nature of works Works Start Finish Traffic Management
City Fibre Salamander Street Installing new fibre optic cable TBC TBC Two way temporary traffic signals
City Fibre East Hermitage Place Installing new fibre optic cable 14/07/2019 17/07/2019 Three way temporary traffic signals
Scottish Power Albert Street Main Cable repair 15/07/2019 19/07/2019 Parking Restriction only
Scottish Power Constitution Street Install new service 19/07/2019 23/07/2019 Parking Restriction only
Scottish Power Pilrig Street at Dryden Street Excavate footway to replace joint TBC TBC Parking Restriction only
Scottish Gas Networks Newhaven Road at Graham Street Install new connection to gas main 14/07/2019 30/07/2019 Three way temporary traffic signals
Scottish Gas Networks North Junction Street at Ferry Road Replace existing gas main 14/07/2019 30/07/2019 Three way temporary traffic signals
Virgin Media Lindsay Road at Sandpiper Drive Install new service 15/07/2019 19/07/2019 Lane restrictions and local diversion

Graham Hall – FIHE – Senior Transport Team Leader – Place – City of Edinburgh Council – North East Locality, 101 Niddrie Mains Rd, Edinburgh, EH16 4DS – Tel: 0131 469 3926 – Northeast.transport@edinburgh.gov.uk

Please note: all correspondence should be sent to Northeast.transport@edinburgh.gov.uk

Albert Street – concept testing

Text and photos are from a PDF issued by Edinburgh Council.

Please could local residents feedback on the success or otherwise of the following scheme to planning.lccc@leithcentralcc.co.uk.

Click the images to see the full-size images in new windows.

A concept testing for the communal bin review project has been implemented in Albert Street to test the project aims:

  1. Increase and improve recycling services to residents in multi-occupancy and flatted properties providing fully integrated waste and recycling service (each location aiming to have residual waste, recycling, food waste and glass)
  2. Review the existing bin locations to develop more formalised collection hubs to improve the perception of the service and enhance the streetscape
  3. Improve overall recycling performance, customer satisfaction and service reliability

Continue reading

LCCC January 2019 approved minutes

Minutes of the ordinary meeting of Leith Central Community Council, held in Nelson Hall, McDonald Road library on Monday 21 JANUARY 2019 at 7:00pm

Actions and decisions are red italic. nem con means that no-one spoke or voted against a decision. Continue reading

LCCC October meeting agenda

Agenda for Meeting of Leith Central Community Council

Monday, 15 October 2018 at 7pm McDonald Road Library, Nelson Hall Continue reading

LCCC August approved minutes

Minutes of the ordinary meeting of Leith Central Community Council, held in Nelson Hall, McDonald Road library on Monday 20 August at 7:00pm Continue reading

LCCC DRAFT minutes: February 2018

Please note that these are draft minutes, and may not be take as authoritative unless approved at LCCC’s next meeting.  Continue reading

LCCC minutes: November 2017

Minutes of the ordinary meeting of Leith Central Community Council, held in Nelson Hall, McDonald Road library on Monday 27 November 2017 at 7:00pm

Actions and decisions are red underlined. nem con means that no-one spoke or voted against a decision. URLs added by minutes secretary. Continue reading