Community Councils Together on Trams/Trams Team meeting, 29 October 2020

Minutes of the Community Councils Together on Trams/Trams Team meeting (Construction Phase) via Google Meet on Thursday 29 October 2020 at 5:30pm Continue reading

Community Councils Together on Trams/Trams Team meeting, 27 August 2020

Minutes of the Community Councils Together on Trams/Trams Team meeting (Construction Phase) via Google Meet on Thursday 27 August 2020 at 5:30pm Continue reading

Community Councils Together on Trams/Trams Team meeting, 30 July 2020

Minutes of the Community Councils Together on Trams/Trams Team meeting (Construction Phase) via Google Meet on Thursday 30 July 2020 at 5:30pm Continue reading

Community Councils Together on Trams/Trams Team meeting, 25 June 2020

Minutes of the Community Councils Together on Trams/Trams Team meeting
(Construction Phase) via Google Meet on Thursday 25 June 2020 at 5:30pm Continue reading

Trams to Newhaven newsletter, 19 June 2020

Unfortunately, the newsletter was not published with a link to a version viewable in a browser. LCCC has replicated the text and links in the newsletter, for the information of its online followers.
Continue reading

Trams: shut-down plans overview (27 March)

(from the Trams to Newhaven newsletter dated 27 March)

Construction on Edinburgh’s Trams to Newhaven project will stop this week to protect the safety of workers and residents during the current Coronavirus outbreak.

The Council’s decision to instruct contractors Morrison Utility Services (MUS) and Sacyr Farrans Neopul (SFN) to cease site works follows advice from Scotland’s First Minister that all construction sites should close, unless the project being delivered is essential, such as a hospital.

SFN and MUS will make sites on Leith Walk, Constitution Street, Lindsay Road and Ocean Drive safe and secure by the end of the week before shutting down. There will be contractors on site as necessary for safety and security checks.

Emergency services have access to all sites at all times should they require it.

Work will continue off-site where this can be done remotely,  including design, planning and scheduling, as well as drawing up a remobilisation strategy for returning to the site once restrictions are lifted. The project team will also be closely liaising with MUS and SFN to look at ways of mitigating the impact of work stopping on the wider project.

Community Councils Together on Trams/Trams Team meeting, 27 February 2020

Minutes of the Community Councils Together on Trams/Trams Team meeting (No 2 Construction Phase) at 165 Leith Walk on Thursday 27 February at 5:30pm Continue reading

Community Councils Together on Trams/Trams Team meeting, 30 January 2020

Minutes of the Community Councils Together on Trams/Trams Team meeting (No 1 Construction Phase), at 200 Bonnington Rd, on Thursday 30 January at 5:30pm Continue reading

Preparatory works for Trams to Newhaven continue with vibration testing

(adapted from an email from Trams to Newhaven: view the original at https://mailchi.mp/7f4d38afd7a4/trams-to-newhaven-update-february-2019-final-business-case-233657)

Ground and Site Investigation Works update

Ground and site investigation works along the route are now in the final stages, with the last of the scheduled works due to complete in week commencing 22 July 2019.
The essential pre-enabling works, being carried out by the tram project’s Systems and Infrastructure contractor Sacyr, Farrans, Neopul (SFN), involves SFN carrying out detailed ground investigation surveys at 25 sites on the route. The work is being carried out in sections of approximately 100 metres at a time and under localised lane closures.
The purpose of ground investigation works is to determine the ground conditions along the route so that the project’s final design can be confirmed. SFN have been checking, among other things, the depth of the bedrock. This will allow us to better understand how deep tram infrastructure foundations need to be, as well as the dimensions of the ‘track slab’, which will be laid beneath the tram tracks.

Continue reading

Tram Diversion Route Resurfacing Work – Revised Programme

(from an email from Edinburgh Council, time-stamped Wed, 3 Jul 2019 at 15:51)

I write to provide an update to my ongoing carriageway resurfacing programme in and around Leith prior to the commencement of the work to extend the tram to Newhaven.

Works on site at Pilrig Street junction, Dalmeny Street and East London Street are due to complete at the end of next week (Friday 12 July) after which time the main contractor has a company recess for 2 weeks.

On returning to site on the 29 July, the work to redesign the junction at Duke Street and Easter Road will fully commence (some preparatory work will take place next week) while the majority of work ongoing elsewhere will be predominantly carriageway resurfacing work.

To this effect, please find below a basic table detailing the proposed locations, dates and traffic management for the resurfacing work and I have also attached the full programme in the form of a Gantt chart. I will caveat this and remind everyone that dates are approximate as any delays can have a knock on effect, however the order of work should remain the same and I will update EdinTravel as works progress.

I will also explain that the programme has extended due to additional work being requested and some issues on site with traffic signal installations however the main resurfacing work should throw up little in the way of unforeseen delays and there will be no further additional work included in the programme unless it is deemed important and we create space in the existing programme. We also remain in full contact with the team leading the Tram extension with regards their preparatory work and start date.

As before, residents and traders will receive notices prior to the start of work in their area with more specific details, and I will forward a copy of these notices on as appropriate. If you have any queries or concerns, please do not hesitate to contact me.

Month Date (Duration) Location Time Proposed Traffic Management
July 9 (2 days) East London Street Day Road Closure
29 (7 days) North Leith Sands Day Road Closure
29 (35 days) Duke Street R’about Redesign Day Retain roundabout as long as possible
August 7 (5 days) Great Junction Street Day Southbound loop using Henderson?
7 (9 days) Duncan Place Day Road Closure
8 (21 days) Links Place Traffic Islands Day Road Narrowing
15 (4 days) Gordon Street Day Road Closure
20 (3 days) Ocean Drive Day Road Closure.1 side at a time.
20 (12 days) Pilrig Street Day Road Closure in 2 phases
26 (6 days) Annandale Street Day Road Closure
September 2 (12 days) Bonnington Road Night Road Closure in 2 phases
9 (5 days) Broughton Street Night Road Closure
18 (12 days) Newhaven Road Night Road Closure in 2 phases
20 (21 days) Easter Road Night Phased road closures, road narrowing
October 10 (12 days) Broughton Road Night Road Closure in 2 phases
17 (2 days) East Hermitage Pl Junction Night 3 phase TTL’s – Close Links Gdns
28 (5 days) Portland Place Night Eastbound Closure using Ocean Drive
28 (10 days) Links Place Night Road Closure in 2 phases
November 4 (6 days) Academy Street Night Road closure, Duke St eastbound closure

Kind regards

Steven Blacklaw ¦ Engineer – Transport Design & Delivery
Place ¦ Planning & Transport ¦ The City of Edinburgh Council ¦ G4, Waverley Court, 4 East Market Street, Edinburgh EH8 8BG
Tel 0131 529 3252 steven.blacklaw@edinburgh.gov.uk