Leith Programme Stakeholder Update 109: Phase 4 (Iona Street to Brunswick Street)

(adapted from an email sent by Michael Motion of Turner & Townsend at 14:51 on 8 September. )

Dear Stakeholder

Our contractor, Crummock, returned to site as of Monday 4th September to remobilise for the completion of the Phase 4 scope of works. At that time, Brunswick Road was closed to accommodate the site compound, and will remain so until the works are completed. Iona Street was also closed to allow commencement of works to realign the kerb line, commence the road surfacing works including the raised table construction and to complete the pavement slabbing. It is likely this will take up to 3 weeks to complete, during which time Iona Street will remain closed.

In addition to the above, we are also working in the following areas:

  • Brunswick Street junction to complete the remain footpath slabbing to the S/E corner
  • Croall Place to complete the remaining Scottish Water rectification works, and to resolve surface water drainage issues
  • 2 nr road crossings on Leith Walk, north and south of Albert Street.

Continue reading

Leith Programme Stakeholder Update 107: Phase 4 (Iona Street to Brunswick Street)

 (adapted from an email from Michael Motion, Senior Project Manager at Turner & Townsend, sent at 16:51 on 21 August 2017)

As of Monday 4th September, following the Edinburgh festival embargo, our Contractor, Crummock, will be returning to Leith Walk to complete Phase 4 of the Leith Programme.  We anticipate completing these works by Friday 3rd November (being an 8 week construction programme).  Continue reading

Leith Programme Stakeholder Update 106: Phase 4 (Pilrig Street to McDonald Road)

(adapted from an email sent by Michael Motion of Turner & Townsend at 18:00 on 8 August. We apologise for the late posting of this news: our web-weaver was on holiday.)

Dear Stakeholder,

Leith Programme Phase 4 is currently observing the Edinburgh Festival embargo on road works within the city and, as such, has now demobilised fully from Leith Walk and Iona Street.  The Contractor will return to site to re-mobilise and commence the remaining works as of Monday 28thAugust.  Continue reading

Leith Programme Stakeholder Update 100: Phase 4 (Pilrig Street to McDonald Road) weekly lookahead

(adapted from an email sent by Michael Motion, Senior Project Manager, Turner & Townsend on 23 June 2017 at 22:45)

Weekly lookahead (w/c 26th June 2017)

Please see below details of works to be undertaken during the course of next week, and the associated worksite locations during the course of next week:

  • Complete grouting to the slabbed paving at the Library corner and open up areas to pedestrians where safe to do so
  • Commence paving to the N/W corner of Croall Place (West side of Leith Walk)
  • Commence paving to Brunswick Street footpath at the junction with Leith Walk
  • Continue paving to the east side of Leith Walk
  • Kerb realignment, and commence kerb laying at Brunswick Street junction
  • Continue works to the road crossings at McDonald Road junction, excavating the tracks and installing ducts

165 Leith Walk – Former Tram Depot Demolition

The former tram depot, located at 165 Leith Walk, is due for demolition: further communication will follow regarding the programme for these works in the coming weeks. The area will be cleared and a creative workspaces project will occupy part of this site.

The smaller building at the front of the former depot (165a Leith Walk) will be retained and refurbished to create a pilot partnership hub delivering local services.  The project is a collaboration between site owners, The City of Edinburgh Council and local arts trust, Out of the Blue.

The project team intends to hold a drop-in community event on 28th June, between 4.30pm – 7.00pm, in the McDonald Road Library.  At this event, there will be an opportunity to find out more about these proposals and to ask any questions.

Should you have any queries or concerns with regards to the above, please do not hesitate to contact me direct either at this Email or at leith.programme@edinburgh.gov.uk

Kind regards

Michael Motion
Senior Project Manager, Infrastructure, Turner & Townsend

Leith Central Community Council: ‘shocked by new hold up to long-overdue Leith Walk repair works’

Statement for immediate release

The email announcing that the contractor for the current phase of the Leith Walk repair works (Iona Street to Brunswick Street) has gone into administration came yesterday late afternoon.

There have been indications for a while that work had slowed down, but this latest development has come as a complete shock. We are seeking urgent clarification on how this will impact on the current work sites in various states of completion south of Pilrig Street and the Iona Street compound, and – most importantly – on the overall progress of getting the Leith Walk works completed all the way to Picardy Place roundabout.

We understand that prior to the contract being awarded comprehensive assessments of the contractor’s financial stability were obtained by the Council. This being so, this would be the first time in the 10 year saga of Leith Walk on/off repairs that the Council does not have to shoulder the blame for the delays and costs that no doubt will come in the wake of this latest development.

Whether there will be further reputational damage will depend entirely on how quickly this situation is recovered, and the relevant clauses in the contract:

  • Is there a sufficiently sized performance bond in place, shielding the project from any financial fallout?
  • Is the works documentation up to date, to allow work to be picked up smoothly by replacement contractors?
  • If the works do not continue in the immediate future with a new contractor and complete before the summer break as planned, will residents and businesses be compensated?
  • Will the various work sites be supervised and protected adequately in the meantime?
  • Will the snagging of the completed works around Pilrig Street be addressed promptly to restore confidence?

It has been said that one should ‘never let a crisis go to waste’. Is this the wake up call that was needed to make the reinstatement of one of Edinburgh’s top three streets a top Council priority?

– ends –

Leith Programme stakeholder update: Pilrig St to McDonald Rd, St James, Trams to Newhaven

(adapted from an email sent by Michael Motion of the Leith Programme at 15:58 on 2017_03_16)

 

Phase 4 update (Pilrig Street to McDonald Road)

The upgrade of the Pilrig Street junction is now complete, and the junction has been re-opened to traffic as of 16th March. Works will now continue on Leith Walk as part of the Pilrig Street to MacDonald Road phase of the Leith Programme. The footpath up to Middlefield and outside Sainsbury’s, and completion of outstanding Crighton Place works, which were previously delayed due to Scottish Water infrastructure works, will be the focus over the coming weeks. The Leith Programme Phase 4 end date remains summer 2017.

In addition to the above, and commencing as of Monday 27th March, CEC will be installing a number of planters and trees to Leith Walk at various locations north of Pilrig Street. Continue reading

Stakeholder Update 93: Phase 4 (Pilrig Street to McDonald Road) and Phase 5 Traffic Regulation Order (Brunswick Street to Montgomery Street)

(adapted from an email from Michael Motion, of Turner & Townsend Limited, sent on 17 January 2017 at 12:55) This post is not written by Leith Central Community Council, does not necessarily reflect LCCC’s opinions and policies, and is for information only. 

The contractor commenced back on site on 5th January, carrying out site set-up on Iona Street as before and stakeholder communication, following which the works to the Pilrig Street junction commenced with a closure of Pilrig Street as of the 9th January for a period of around 8 weeks (early March completion).  These works will also include works to the Iona Street junction and the surfacing of Leith Walk at these junctions.  This will be the main focus of our Contractors’ work at this time as we seek to minimise disruption to pedestrians and traffic by opening a number of work sites concurrently.  Work sites will then progress south on Leith Walk from Pilrig Street to McDonald Road as originally envisaged, with any additional work sites being opened only where it is felt there is a benefit to the Project without adversely affecting the use of the street.

Progress towards the end of last year was disrupted by 3rd party utility operations, and we will again be required to accommodate their works during the course of the Phase 4 Contract, while trying at all times to minimise the impact on the Programme.

A report detailing the responses from the statutory consultation on the Leith Programme Phase 5 will be considered at the Transport and Environment Committee on 17 January.  Continue reading