Leith Programme Stakeholder Update 114: Phase 4 (Iona Street to Brunswick Street)

(adapted from an email from Michael Motion, Senior Project Manager, Infrastructure, Leith Programme Project Team, sent on 2017_10_06 at 14:30)

This email contains information on

  • Proposed works w/c 9th October 2017
    • Road closures
    • Proposed works / worksite locations
  • Two-stage right turn for cyclists – junction of Leith Walk and McDonald Road/Brunswick Road
  • New segregated cycle lanes on Leith Walk
  • Picardy Place design update

Continue reading

Leith Programme Stakeholder Update 111 – Phase 4 (Iona Street to Brunswick Street)

(adapted from an email sent by Michael Motion, Senior Project Manager, Infrastructure, Turner & Townsend at 17:08 on 2017_09_22)

Completion of the road surfacing works will be noticeable as we complete areas and move the major worksites southwards towards McDonald Road and Brunswick Street. With that being the case, we will now be closing both McDonald Road and Brunswick Street junctions on Wednesday morning, 27th September with local diversions put in place. This will coincide with the opening up of both Iona Street and Albert Street. McDonald Road and Brunswick Street will remain closed until completion of all works by the end of October, as will Brunswick Road where the site compound is located. Continue reading

Leith Programme Stakeholder Update 110 – Phase 4 (Iona Street to Brunswick Street)

(adapted from an email from Michael Motion,  Senior Project Manager, Infrastructure, Turner & Townsend, sent at 11:31 on 2017_09_17)

Proposed works and worksite locations for w/c 18th September

  • Kerb realignment has been completed at the Iona Street junction, and the footpath slabbing works will progress this week
  • Completion of the footpath slabbing to the S/E corner of the Brunswick Street junction will continue this week
  • Continuing the Scottish Water works at Croall Place, followed by the footpath reinstatement works
  • Albert Street will close today for 2 weeks to accommodate the Leith Walk road re-surfacing works with associated traffic management and local diversions in place to accommodate these works
  • Road surfacing works are continuing north to south on Leith Walk, are progressing well, and will be focussed on the East side going past Albert Street this week

Continue reading

Leith Programme Stakeholder Update 107: Phase 4 (Iona Street to Brunswick Street)

 (adapted from an email from Michael Motion, Senior Project Manager at Turner & Townsend, sent at 16:51 on 21 August 2017)

As of Monday 4th September, following the Edinburgh festival embargo, our Contractor, Crummock, will be returning to Leith Walk to complete Phase 4 of the Leith Programme.  We anticipate completing these works by Friday 3rd November (being an 8 week construction programme).  Continue reading