Leith Programme stakeholder update: Pilrig St to McDonald Rd, St James, Trams to Newhaven

(adapted from an email sent by Michael Motion of the Leith Programme at 15:58 on 2017_03_16)

 

Phase 4 update (Pilrig Street to McDonald Road)

The upgrade of the Pilrig Street junction is now complete, and the junction has been re-opened to traffic as of 16th March. Works will now continue on Leith Walk as part of the Pilrig Street to MacDonald Road phase of the Leith Programme. The footpath up to Middlefield and outside Sainsbury’s, and completion of outstanding Crighton Place works, which were previously delayed due to Scottish Water infrastructure works, will be the focus over the coming weeks. The Leith Programme Phase 4 end date remains summer 2017.

In addition to the above, and commencing as of Monday 27th March, CEC will be installing a number of planters and trees to Leith Walk at various locations north of Pilrig Street. Continue reading