Proposed waiting/loading restriction changes to facilitate footway widening – Great Junction Street

Copied from an email from CEC’s Spaces for People. LCCC position on such rushed ‘consultations‘ (for example, in this post) remains that ‘LCCC regrets that the procedural shortcomings of a foreshortened consultation process may impinge on the quality of the proposed measures and undermine public trust and support.

EDIT: Great Junction St is not in LCCC’s area, but it is quite possible that the changes will impact the area.

Covid-19 Cycling and Walking Emergency Response Measures

Proposed waiting/loading restriction changes to facilitate footway widening – Great Junction Street

Following our email of 26 June advising that we would notify you once further details were available for the proposals above, we are pleased to be able to provide these now. We are aware that you were initially given proposals for Great Junction Street and Easter Road in a single notification, however in an effort to provide details at the earliest opportunity these have been separated and plans for Easter Road will be issued as soon as they are available.

We would suggest that you view the plan to see the detail of what is proposed.

map of proposals for Great Junction St and Easter Rd

Click the graphic to see the full PDF. LCCC’s web-weaver is not happy that the map does not include a key.

Continue reading

Covid-19 measures for Easter Road, Gt Junction St: LCCC’s response

Dear Councillor Macinnes

We acknowledge receipt of the email below and the attached map indicating that there are proposed Covid-19 Emergency Road Measures for Easter Road and Great Junction Street. However, we await a further Council email explaining exactly what is proposed, as all we have received is a map with a few red lines, no legend and no site-specific details. We don’t really understand how we are supposed to respond this, as it adds nothing to what was in the outline proposals approved on 14 May. Has no further detailed planning been done in the intervening five weeks?

We are being told that there is no time for normal expectations associated with consultations and are asked if we want to raise any issues.

The main issue we have is with the absence of a credible process: I am sure everyone on the extensive (GDPR-compliant?) mailing list below is a very busy person and may not be able to respond within the given timescale to potentially very complex proposals (let alone understand them in the absence of concrete details) with all their knock-on effects into neighbouring streets and on a wide variety of legitimate (and sometimes vulnerable) users. Where do the proposals go, if the physical distancing guidance is reduced to 1m in early July, as flagged up by the First Minister last week? Will a rushed implementation of measures which – if well-planned and consulted upon may well have merit – not undermine wider public support for a more pedestrian-friendly environment in the longer term?

With this qualification, we make the following observations. Continue reading

Community Councils Together on Trams/Trams Team meeting, 27 February 2020

Minutes of the Community Councils Together on Trams/Trams Team meeting (No 2 Construction Phase) at 165 Leith Walk on Thursday 27 February at 5:30pm Continue reading

Constitution Street tram-construction start

(adapted from an email from the Trams to Newhaven project. Constitution St is not in LCCC’s area, but LCCC residents and businesses may wish to know the following.)

The Tram to Newhaven project team is hosting a drop-in event on Thursday 7 November from 12pm – 7.30pm at South Leith Parish Church where residents and businesses can come and meet the team who can answer any queries they might have about the planned works.

The first phase of work to take trams to Newhaven will start on Constitution Street on 18 November 2019. Continue reading

Community Councils Together on Trams/Trams Team meeting, 26 September 2019

Minutes of the Community Councils Together on Trams/Trams Team meeting, at 200 Bonnington Road, on Thursday 26 September 2019 at 5:30pm

Actions and decisions are red italic. Continue reading

Tram Diversion Route Resurfacing Work – Revised Programme

(from an email from Edinburgh Council, time-stamped Wed, 3 Jul 2019 at 15:51)

I write to provide an update to my ongoing carriageway resurfacing programme in and around Leith prior to the commencement of the work to extend the tram to Newhaven.

Works on site at Pilrig Street junction, Dalmeny Street and East London Street are due to complete at the end of next week (Friday 12 July) after which time the main contractor has a company recess for 2 weeks.

On returning to site on the 29 July, the work to redesign the junction at Duke Street and Easter Road will fully commence (some preparatory work will take place next week) while the majority of work ongoing elsewhere will be predominantly carriageway resurfacing work.

To this effect, please find below a basic table detailing the proposed locations, dates and traffic management for the resurfacing work and I have also attached the full programme in the form of a Gantt chart. I will caveat this and remind everyone that dates are approximate as any delays can have a knock on effect, however the order of work should remain the same and I will update EdinTravel as works progress.

I will also explain that the programme has extended due to additional work being requested and some issues on site with traffic signal installations however the main resurfacing work should throw up little in the way of unforeseen delays and there will be no further additional work included in the programme unless it is deemed important and we create space in the existing programme. We also remain in full contact with the team leading the Tram extension with regards their preparatory work and start date.

As before, residents and traders will receive notices prior to the start of work in their area with more specific details, and I will forward a copy of these notices on as appropriate. If you have any queries or concerns, please do not hesitate to contact me.

Month Date (Duration) Location Time Proposed Traffic Management
July 9 (2 days) East London Street Day Road Closure
29 (7 days) North Leith Sands Day Road Closure
29 (35 days) Duke Street R’about Redesign Day Retain roundabout as long as possible
August 7 (5 days) Great Junction Street Day Southbound loop using Henderson?
7 (9 days) Duncan Place Day Road Closure
8 (21 days) Links Place Traffic Islands Day Road Narrowing
15 (4 days) Gordon Street Day Road Closure
20 (3 days) Ocean Drive Day Road Closure.1 side at a time.
20 (12 days) Pilrig Street Day Road Closure in 2 phases
26 (6 days) Annandale Street Day Road Closure
September 2 (12 days) Bonnington Road Night Road Closure in 2 phases
9 (5 days) Broughton Street Night Road Closure
18 (12 days) Newhaven Road Night Road Closure in 2 phases
20 (21 days) Easter Road Night Phased road closures, road narrowing
October 10 (12 days) Broughton Road Night Road Closure in 2 phases
17 (2 days) East Hermitage Pl Junction Night 3 phase TTL’s – Close Links Gdns
28 (5 days) Portland Place Night Eastbound Closure using Ocean Drive
28 (10 days) Links Place Night Road Closure in 2 phases
November 4 (6 days) Academy Street Night Road closure, Duke St eastbound closure

Kind regards

Steven Blacklaw ¦ Engineer – Transport Design & Delivery
Place ¦ Planning & Transport ¦ The City of Edinburgh Council ¦ G4, Waverley Court, 4 East Market Street, Edinburgh EH8 8BG
Tel 0131 529 3252 steven.blacklaw@edinburgh.gov.uk

More detail on carriageway resurfacing works – Summer 2019/20

Following on from this post, Edinburgh Council has just sent the following detail about the road resurfacing planned for this summer.

Location Planned Start Date Estimated Duration Work Detail
Broughton Street 28-May + 22 Aug 4 weeks + 2 weeks Pedestrian crossing upgrade + carriageway resurfacing
Albany Street 03-Jun 1 week Carriageway resurfacing
Hopetoun Street 07-Jun 2 days Carriageway resurfacing
Academy Street 11-Jun 1 week Overlay setts
Dalmeny Street 17-Jun 10 days Carriageway resurfacing, overlay setts and minor footway works
East Hermitage Place 26-Jun 3 days Carriageway resurfacing
Portland Place 28-Jun 1 week Carriageway resurfacing
McDonald Road 01-Jul 10 days Footway widening and carriageway patching
Easter Road/Duke Street 01-Jul 8 weeks Junction redesign
East London Street 02-Jul 7 weeks Pedestrian crossing upgrade and carriageway resurfacing
Duncan Place 10-Jul 2 weeks Carriageway resurfacing and minor footway works
Great Junction Street 10-Jul 1 week Carriageway resurfacing
Gordon Street 02-Aug 1 week Carriageway resurfacing
Bonnington Road 08-Aug 3 weeks Carriageway resurfacing
Ocean Drive 08-Aug 3 days Carriageway resurfacing
North Leith Sands 13-Aug 1 week Carriageway resurfacing and minor footway works
Newhaven Road 26-Aug 2 weeks Carriageway resurfacing
Annandale Street 29-Aug 7 weeks New pedestrian crossings and carriageway resurfacing
Broughton Road 05-Sep 2 weeks Carriageway resurfacing
Easter Road 11-Sep 3 weeks Carriageway resurfacing and minor footway works
Links Place 23-Sep 4 weeks Carriageway resurfacing, new traffic island and footway works
Pilrig Street 29-Sep 4 weeks Carriageway resurfacing, new traffic island and footway works

Proposed Carriageway Resurfacing Works – Summer 2019/20

(adapted from an email from Edinburgh Council)

The carriageway on a number of streets in your Ward are due to be resurfaced during the Summer of 2019. The roads affected have been prioritised because of their current condition and because the upcoming tram works will prevent any planned resurfacing work from taking place in and around the proposed tram line during the construction period.

The resurfacing works are planned to start on 27 May and will be carried out during weekdays in separate phases in order to minimise disruption to the public. On some traffic sensitive routes, work may be carried out under nightshift to minimise the impact on traffic. Most roads affected will be fully or significantly resurfaced with a select few being only partially resurfaced or patched as required. There will also be some improvements to pedestrian facilities, traffic signal upgrades and renewal of some street furniture.

Continue reading