Stakeholder Update 116 – Leith Programme – Phase 4

(adapted from an email from Michael Motion of Leith Programme Project Team, sent at 11:54 on 2017_11_23)

In our last communication (27th October) we explained that the Contractor would be commencing the making good of defective works within remote worksites on Leith Walk.  This work is progressing well and we have taken the opportunity to also make good some defects in the work carried out during Phase 2 of the Leith Programme between the Foot of the Walk and Dalmeny Street.

Our current programme is as follows:

  • Replace bus shelter and install bus tracker at Albert Street – Complete
  • Phase 2 remedial works as above – Due to complete by 24th November
  • Make good surfacing to the southbound bus stop bypass at Shrubhill – Due to complete by 1st December
  • Resolve ponding issue to Brunswick Street cycleway – Due to complete by 1st December
  • Remove temporary footway ramps at Iona Street and Albert Street – Due to complete by 1st December
  • General making good works to kerbs and road/footway chambers – Due to complete by 1st December

Thank you for bearing with us as we complete these works.

Should you require any further information, please do not hesitate to contact the Leith Programme Email address: leith.programme@edinburgh.gov.uk

Kind regards

Michael Motion
Leith Programme Project Team

Leith Programme Stakeholder Update 114: Phase 4 (Iona Street to Brunswick Street)

(adapted from an email from Michael Motion, Senior Project Manager, Infrastructure, Leith Programme Project Team, sent on 2017_10_06 at 14:30)

This email contains information on

  • Proposed works w/c 9th October 2017
    • Road closures
    • Proposed works / worksite locations
  • Two-stage right turn for cyclists – junction of Leith Walk and McDonald Road/Brunswick Road
  • New segregated cycle lanes on Leith Walk
  • Picardy Place design update

Continue reading

Leith Programme Stakeholder Update 113 – Phase 4 (Iona Street to Brunswick Street)

(adapted from an email from Michael Motion, Senior Project Manager, Infrastructure, Leith Programme Project Team, sent at 11:01 on 2017_10_02)

Proposed works w/c 2nd October 2017

 Road closures

  • Albert Street (planned re-opening date Tuesday 10th October)
  • Brunswick Road (will remain closed until completion of the project at the end of October)
  • McDonald Road (will remain closed until completion of the project at the end of October)
  • Brunswick Street (planned re-opening date Wednesday 18th October 2017)

Continue reading

Leith Programme Stakeholder Update 112 – Tram to Newhaven & Leith Programme

(adapted from an email from Michael Motion, Senior Project Manager, Infrastructure, Leith Programme Project Team, on 2017_09_27 at 16:35)

Edinburgh Tram

As you may be aware, the Outline Business Case for taking trams to Newhaven was approved on the 21st of September by the City of Edinburgh Council.  You can see the Outline Business Case and the supporting report here under Reports and item 8·4.

A comprehensive tendering process will now get under way to secure a potential contractor partner for the project, with councillors due to make a final decision on taking the tram to Newhaven in autumn 2018 to allow construction to start in early 2019. Continue reading

Leith Programme Stakeholder Update 111 – Phase 4 (Iona Street to Brunswick Street)

(adapted from an email sent by Michael Motion, Senior Project Manager, Infrastructure, Turner & Townsend at 17:08 on 2017_09_22)

Completion of the road surfacing works will be noticeable as we complete areas and move the major worksites southwards towards McDonald Road and Brunswick Street. With that being the case, we will now be closing both McDonald Road and Brunswick Street junctions on Wednesday morning, 27th September with local diversions put in place. This will coincide with the opening up of both Iona Street and Albert Street. McDonald Road and Brunswick Street will remain closed until completion of all works by the end of October, as will Brunswick Road where the site compound is located. Continue reading

Leith Programme Stakeholder Update 110 – Phase 4 (Iona Street to Brunswick Street)

(adapted from an email from Michael Motion,  Senior Project Manager, Infrastructure, Turner & Townsend, sent at 11:31 on 2017_09_17)

Proposed works and worksite locations for w/c 18th September

  • Kerb realignment has been completed at the Iona Street junction, and the footpath slabbing works will progress this week
  • Completion of the footpath slabbing to the S/E corner of the Brunswick Street junction will continue this week
  • Continuing the Scottish Water works at Croall Place, followed by the footpath reinstatement works
  • Albert Street will close today for 2 weeks to accommodate the Leith Walk road re-surfacing works with associated traffic management and local diversions in place to accommodate these works
  • Road surfacing works are continuing north to south on Leith Walk, are progressing well, and will be focussed on the East side going past Albert Street this week