Tag Archives: coronavirus

Trams to Newhaven newsletter, 19 June 2020

Unfortunately, the newsletter was not published with a link to a version viewable in a browser. LCCC has replicated the text and links in the newsletter, for the information of its online followers.
Continue reading

LCCC May 2020 minutes

Due to the limitations of online meetings, we are only recording those who were present at or sent apologies for such meetings.

This meeting was for members only, so any decision recorded below may not be binding. Similarly, the LCCC June meeting may not have been empowered to approve the minutes below.

Minutes of the ordinary meeting of Leith Central Community Council, held via Zoom on Monday 18 May 2020 at 7:00pm

Actions and decisions are red italic. nem con means that no-one spoke or voted against a decision. Continue reading

LCCC April 2020 minutes

Due to the limitations of online meetings, we are only recording those who were present at or sent apologies for such meetings.

This meeting was for members only, so any decision recorded below may not be binding. Similarly, the LCCC June meeting may not have been empowered to approve the minutes below. (These minutes were not published earlier because they were not considered at the May meeting due to an error in circulating the draft.)

Minutes of the ordinary meeting of Leith Central Community Council, held via Zoom on Monday 20 April 2020 at 7:00pm Continue reading

Main construction start – Trams to Newhaven

(Copied from an email from Trams to Newhaven)

The main construction works for the Edinburgh’s Trams to Newhaven project will start from Monday 15 June 2020 in line with the Scottish Government’s Phase 2 ‘soft start to site works (only where physical distancing can be maintained).

Work on the project was stopped at the end of March to comply with Government guidance and to protect the safety of workers and residents during the coronavirus outbreak.

Following the First Minister’s announcement on 21 May of a phased return for construction sites, plans have been drawn up in line with Scottish Government safety guidelines and industry best practice to ensure the safety of workers and the public. At the briefing on 28 May the First Minister confirmed that site preparation could begin and, following the announcement today, main construction works can now start. This will encompass the existing sites on Lindsay Road, Melrose Drive and Constitution Street which will start from Monday 15 June. In addition, main construction works on Leith Walk from Elm Row to Crown Place will start on Monday 22 June.

In advance of this some preparatory works on Leith Walk will start on Monday 15 June 2020 ahead of the installation of traffic management which will begin on the evening of Friday 19 June and be operational from 5am on Saturday 20 June 2020 including Lothian Bus diversions. All traffic management arrangements are made in consultation with key partners in the city, including blue light services and public transport providers, through the Traffic Management Review Panel and are continuously monitored and reviewed to ensure they work as effectively as possible.

All works will be carried out through physical distancing and additional measures to protect workers’ health will include daily briefings, continuous on-site inspections and health and safety ‘ambassadors.’ The numbers of workers on-site will be kept to a minimum and a large proportion of the project office staff will continue to work from home. While physical distancing will be a key principle of construction working, workers will also have access to personal protection equipment (PPE) which they may choose to wear as an additional precaution if they wish. It should be noted that it may take time for the sites to become fully operational.

The logistic hubs at the Mitchell Street, Foot of the Walk, Dalmeny Street, Albert Street and Montgomery Street will re-open on Monday 22 June to support local businesses with deliveries and despatches. All communal bins that are currently situated on Leith Walk will be moved to the side streets.

If you have any queries please do not hesitate to get in contact.

Chris Wilson

For information

The Scottish Government’s phased approach to construction details six key phases to ensure work is carried out in a safe way. These are:

  • Phase 0: Planning
  • Phase 1: Covid-19 Pre-start Site preparation
  • Phase 2: ‘Soft start’ to site works (only where physical distancing can be maintained)
  • Phase 3: Steady state operation (only where physical distancing can be maintained)
  • Phase 4: Steady state operation (where physical distancing can be maintained and/or with PPE use)
  • Phase 5: Increasing density/productivity with experience

Proposed Bus, Cycle and Taxi gates, segregated cycle lanes and Footway widening on Forrest Road, The Mound, South Bridge and George IV Bridge (and North Bridge)

LCCC received the email below on 8 June 2020 along with drawings for Forrest Road, The Mound, George IV Bridge, South Bridge (a fifth drawing for North Bridge was obtained separately from NTBCC’s website), inviting us to respond within five business days to the proposals.

Given that five days are insufficient to allow for a considered response to complex proposals, even at the best of times, we wrote back (see below) stating that LCCC is not in a position to respond formally and substantially while much of public and democratic life is curtailed under emergency powers and LCCC is not able to hold public, properly constituted meetings.

LCCC regrets that the procedural shortcomings of a foreshortened consultation process may impinge on the quality of the proposed measures and undermine public trust and support.

Residents may wish to respond individually. If so, write to spacesforpeople@edinburgh.gov.uk by 5pm on Monday, 15 June 2020.

Click any thumbnail to see the full-size PDF in a new tab or window.


TDD-637129-04-North-Bridge

TDD-637129-1200-07 South Bridge

TDD-637129-1200-09 George IV Bridge

TDD-637129-1200-10 The Mound

TDD-637129-1200-11 Forrest Road

Continue reading

Site preparation start – Trams to Newhaven

From an email from Trams to Newhaven

Construction site preparation works for the Edinburgh’s Trams to Newhaven project will start on Monday, 1 June 2020 in line with the Scottish Government’s Phase 1 pre-start site preparation.

Work on the project was stopped at the end of March to comply with Government guidance and to protect the safety of workers and residents during the coronavirus outbreak.

Following the First Minister’s announcement on 21 May of a phased return for construction sites, plans have been drawn up in line with Scottish Government safety guidelines and industry best practice to ensure the safety of workers and the public. At the briefing on 28 May the First Minister confirmed that site preparation could begin.

In advance of the main work beginning, works to prepare construction sites and project offices will include the introduction of infection control stations, additional water stations and toilet facilities for workers within the site and in the project office, and ensuring all office workspaces and facilities are set up appropriately. Other works on site will include the removal of the protective in-fill material that was used to ensure the work site remained safe and protected during the shutdown.

Measures to protect workers’ health will include daily briefings, continuous on-site inspections and health and safety ‘ambassadors.’ The numbers of workers on-site will be kept to a minimum and the majority of project office staff will continue to work from home.

Once the construction industry is given the approval to move to Phase 2, works on the existing sites will recommence and the Leith Walk construction site will be established as planned prior to site shutdown.

Any commencement of main works will be subject to the Scottish Government giving approval to move to Phase 2 of their construction guidelines which states: ‘soft start to site works (only where physical distancing can be maintained)’.

The project team has been working on plans to mitigate the impact of the enforced shutdown as a result of COVID 19 on the programme and budget. Despite the current circumstances the project continues to operate within its £207·3m budget. The project is paid for by borrowing monies that are repaid over a 30-year period through future revenues from customers.

If you have any queries please do not hesitate to get in contact

Regards

Chris Wilson

For information

The Scottish Government’s phased approach to construction details six key phases to ensure work is carried out in a safe way. These are:

  • Phase 0: Planning
  • Phase 1: Covid-19 Pre-start Site preparation
  • Phase 2: ‘Soft start’ to site works (only where physical distancing can be maintained)
  • Phase 3: Steady state operation (only where physical distancing can be maintained)
  • Phase 4: Steady state operation (where physical distancing can be maintained and/or with PPE use)
  • Phase 5: Increasing density/productivity with experience

Milan (Senior Welfare Organisation) COVID alternative services

LCCC has received the following email from ‘Milan (Senior Welfare Organisation)’. Reproducing the email is not a recommendation, and saying that is not a criticism – it’s just that LCCC’s web weaver doesn’t know anything about this organisation, except that it is registered with Companies House and with the Scottish Charity Regulator.

I hope this email finds you all well during these unprecedented times.  I am the manager of a registered charitable organisation (SCO23030) based  in Norton Park Edinburgh. We provide day care provision for elderly South Asian communities and due to closure of our day care services due to COVID_19 we are providing the alternative services.

  • Contactless Delivery of food parcels
  • Contactless Delivery of hot meals
  • Remote information/advice in community languages
  • Emotional support to older people
  • Supporting carers of older people though the pandemic situation

I would be most grateful if you could please add us to your website or any information leaflets you have so we are able to reach out to people in need

Pease do not hesitate to contact me if you require any further clarification

Kind regards

Sophia
sophia@milanswc.org

Active travel update

On Friday, the Council launched a campaign encouraging everyone to be considerate of other people and follow Scottish Government guidance when enjoying their outdoor exercise and travel.

The press release which was published on Friday can be found here.

Increase in people using off-road paths and parks

Since restrictions were introduced to help manage the coronavirus outbreak, there’s been an increase in people using the city’s network of paths, as well as parks, as part of their daily exercise and for travelling to work or local amenities – with up to five times their normal use.

Data up to week five of lockdown shows increases on the Union Canal towpath, with 17% growth in pedestrian numbers at Harrison Park, whilst cycling numbers have grown by 76% at Wester Hailes. On the North Edinburgh Path Network at Rodney St, pedestrian numbers have grown by 14%, cycling numbers by 32%.  At certain times of the week, especially weekends, much bigger increases have been recorded.

While it’s great that the routes are popular and well-used, we want to make sure that everyone can undertake and enjoy their daily exercise and travel in safety and comfort.

Paths for everyone code of conduct

The campaign will direct people to the Paths for Everyone section of the Council’s webpages, where we hope to be able to display information such as busy routes/times, coming from our pedestrian/cycle counter data.  This aims to encourage people to use alternative routes if they can, or exercise at a less busy time.  Smarter Choices, Smarter Places funding for this project is gratefully received from Paths for All.

About the campaign

example of temporary signageTemporary signage (example on the right: click the thumbnail to see the full-size image) will be rolled out this week, starting on the active travel network entry points, and signage in the parks will follow.  We will be running a complementary social media campaign also, and we would really appreciate your support with sharing this content amongst your followers and networks.

Report issues

There might be local issues that you are aware of where additional signs may help. Please email your suggestions to spacesforpeople@edinburgh.gov.uk.

Wishing you all the best and thank you in advance for your support with our campaign.

Kind regards,

Judith Cowie
‘Smarter Choices, Smarter Places’ Programme Manager
Active Travel
Road Safety and Active Travel
Transport Networks, Place Development
The City of Edinburgh Council
Judith.cowie@edinburgh.gov.uk

 

Where to get help with your gas and electricity concerns

(adapted from an email from Changeworks)

‘As we continue to adjust to Covid-19 we’re all spending more time at home and using more energy than normal. Many households are experiencing financial strain and will be worried about the effect this will have on their energy bills.

Whilst Changeworks is unable to provide face to face outreach services to support people looking for energy and fuel billing/debt advice, we are still here to help. We’ve teamed up with SGN to produce a series of short films providing advice and support on managing energy use and where to get help with heating and electricity concerns.

Our first video – where to get help with your gas and electricity concerns – is now live on YouTube.

Handy links can be found here:

We’ll be publishing three more videos over the next few weeks and we’ll be in touch to share these with you too.

You can also still refer households you think would benefit from energy advice and fuel billing/debt support.