Leith Programme Stakeholder Update 107: Phase 4 (Iona Street to Brunswick Street)

 (adapted from an email from Michael Motion, Senior Project Manager at Turner & Townsend, sent at 16:51 on 21 August 2017)

As of Monday 4th September, following the Edinburgh festival embargo, our Contractor, Crummock, will be returning to Leith Walk to complete Phase 4 of the Leith Programme.  We anticipate completing these works by Friday 3rd November (being an 8 week construction programme).  Continue reading →

LCCC August meeting agenda

Outline Agenda LCCC 21 August 2017

  1. Welcome, introductions, attendance and apologies
  2. Approval of Minutes of 19 June 2017 meeting
  3. Matters Arising
  4. Community Police Officer’s Report
  5. LCCC Office Bearers’ Reports
  6. Planning
  7. Transport
  8. Environment
  9. Councillors’ reports, MSPs’ reports, MP’s report
  10. Open Forum
  11. Bulletin
  12. AOCB
  13. Future Meetings (usually 3rd Monday of the month) and meeting topics/presentations

A detailed agenda will be available nearer the time.

What We Do and When We Meet

We’re here to listen, represent and take action on the things that matter most to the people who live and work in Leith – from planning applications and housing to street cleaning, public transport, green spaces & more.

 

Our meetings are on Every Third Monday, 7pm – 9pm, at the Nelson Hall in McDonald Rd Library. All welcome! There is no meeting in July and December.

The monthly meeting agenda includes updates on policing, planning, local parks, clean streets, and more, with an open forum for residents and businesses to raise questions or concerns.

Sign up to our mailing list.

If you have any questions about LCCC, please contact:

Leith Programme Stakeholder Update 106: Phase 4 (Pilrig Street to McDonald Road)

(adapted from an email sent by Michael Motion of Turner & Townsend at 18:00 on 8 August. We apologise for the late posting of this news: our web-weaver was on holiday.)

Dear Stakeholder,

Leith Programme Phase 4 is currently observing the Edinburgh Festival embargo on road works within the city and, as such, has now demobilised fully from Leith Walk and Iona Street.  The Contractor will return to site to re-mobilise and commence the remaining works as of Monday 28thAugust.  Continue reading →