Leith Programme Stakeholder Update 106: Phase 4 (Pilrig Street to McDonald Road)

(adapted from an email sent by Michael Motion of Turner & Townsend at 18:00 on 8 August. We apologise for the late posting of this news: our web-weaver was on holiday.)

Dear Stakeholder,

Leith Programme Phase 4 is currently observing the Edinburgh Festival embargo on road works within the city and, as such, has now demobilised fully from Leith Walk and Iona Street.  The Contractor will return to site to re-mobilise and commence the remaining works as of Monday 28thAugust.  Continue reading

Stakeholder Update 101: Leith Programme – Phase 4 (Pilrig Street to McDonald Road) Weekly lookahead (w/c 3rd July 2017)

(adapted from an email from Michael Motion, Senior Project Manager, Infrastructure, Turner & Townsend)

With regards to works carried out this week, the contractor has not quite completed the paving works to the library corner, meaning the resource did not commence paving to the N/W corner at Croall Place. As such, we will be on site on Saturday to make-up some of the time lost this week due to the poor weather and to maintain our current programme of works.

In terms of works and worksite locations for next week, please see below:

  • Any final completion/grouting of paving at the library corner
  • Commence paving to the N/W corner on Croall Place West
  • Continue paving to Brunswick Street
  • Continue paving to Leith Walk East side
  • Complete crossing excavations and traffic signal duct installation at Brunswick Road
  • Return to complete duct crossings at the Albert Place pedestrian crossing (unfortunately the crossing will therefore be out of commission for a period of time next week) and just north of Shrub Place Lane

Continue reading