- Welcome, introductions, attendance, apologies
- to note: declarations of interest in any items on the agenda
- to agree: order of business below
- Approval of Minutes of the Ordinary LCCC Meeting on 15 February 2021 meeting
- Matters Arising from previous minutes (and not included on agenda below)
- Community Police Officer’s Report
Tag Archives: Pilrig St
Community Councils Together on Trams/Trams Team meeting, 28 January 2021
Minutes of the Community Councils Together on Trams/Trams Team meeting (Construction Phase) via Google Meet on Thursday 28 January 2021 at 5:30pm
Community Councils Together on Trams/Trams Team meeting, 01 October 2020
Minutes of the Community Councils Together on Trams/Trams Team meeting
(Construction Phase) via Google Meet on Thursday 1 October 2020 at 5:30pm Continue reading
Trams To Newhaven Newsletter: 23rd Oct
The ‘Trams To Newhaven’ team have sent out their fortnightly newsletter, here are some adapted excepts relating to our area;
Leith Central Community Council volunteers continue to liaise with the Trams To Newhaven team and neighbouring community councils. Please visit the “CCTT (Community Councils Together on Trams)” tag on our website to see minutes from previous meetings.
Leith Walk
Site investigation, excavation works and surface water drainage installation is continuing from London Road to Crown Street.
Pilrg Street to Dalmeny Street
This section of works has been handed back to Infrastructure & Systems Contractor, SFN, who will commence the main tram infrastructure works.
McDonald Road
McDonald Road / Leith Walk junction has been shut to accommodate utility diversions as part of the construction programme. These planned works were based on documents given to the project that detailed the locations of utilities in the area. Following excavations of the road we have identified the need for additional electrical utility works to take place.
Pedestrian access will be maintained at all times and Pilrig Street will remain open to help traffic flow in the area. Vehicle access to McDonald Road will remain via Bonnington and Broughton Road.
Trams progress so far
Trams to Newhaven have created this video that provides an update on progress so far. From Newhaven to London Road, get a birds eye view of the project. The video outlines current key areas of the project, including archaeological works, Logistic provisions and approximate locations of the future tram stops.
Murals
As part of the Support for Business package, Trams to Newhaven have commissioned a series of small murals to be painted on utility boxes on Leith Walk and Constitution Street. Working alongside Vue Arts, the project will help exhibit the work of local aspiring and established graffiti and street artists.
You can sign up for the Trams To Newhaven fortnightly newsletter on at edinburgh.gov.uk/tramstonewhaven
Community Councils Together on Trams/Trams Team meeting, 27 August 2020
Minutes of the Community Councils Together on Trams/Trams Team meeting (Construction Phase) via Google Meet on Thursday 27 August 2020 at 5:30pm Continue reading
