Tag Archives: Leith Walk

Preparatory works for Trams to Newhaven continue with vibration testing

(adapted from an email from Trams to Newhaven: view the original at https://mailchi.mp/7f4d38afd7a4/trams-to-newhaven-update-february-2019-final-business-case-233657)

Ground and Site Investigation Works update

Ground and site investigation works along the route are now in the final stages, with the last of the scheduled works due to complete in week commencing 22 July 2019.
The essential pre-enabling works, being carried out by the tram project’s Systems and Infrastructure contractor Sacyr, Farrans, Neopul (SFN), involves SFN carrying out detailed ground investigation surveys at 25 sites on the route. The work is being carried out in sections of approximately 100 metres at a time and under localised lane closures.
The purpose of ground investigation works is to determine the ground conditions along the route so that the project’s final design can be confirmed. SFN have been checking, among other things, the depth of the bedrock. This will allow us to better understand how deep tram infrastructure foundations need to be, as well as the dimensions of the ‘track slab’, which will be laid beneath the tram tracks.

Continue reading

LCCC May 2019 approved minutes

Minutes of the AGM of Leith Central Community Council, held in Nelson Hall, McDonald Road library on Monday 20 May 2019 at 7:00pm

Actions and decisions are red italic. nem con means that no-one spoke or voted against a decision.

The AGM was chaired Cllr Rob Munn. Continue reading

Minutes of the Community Councils Together on Trams/Trams Team meeting, held at 200 Bonnington Road on Wednesday 6 June 2019 at 5:30pm

Actions and decisions are red italic.

1 Abbreviations

BAFO = best and final offer LLCC = Leith Links Community Council
CCTT = Community Councils Together on Trams LW = Leith Walk
CEC = City of Edinburgh Council NTBCC = New Town & Broughton Community Council
CPZ = controlled parking zone OBC = outline business case
CS = Constitution St POLHA = Port of Leith Housing Association
ECI = early contractor involvement SPC = swept-path contract
EIA = environmental impact assessment TAPOG = CEC’s tram all-party oversight group
FBC = full business case TfE = Transport for Edinburgh
ISC = infrastructure and systems contract TN = Trams to Newhaven project
LCCC = Leith Central Community Council TRO = traffic regulation order
LHNCC = Leith Harbour & Newhaven Community Council TT = trams team

TAPOG is CEC’s leader and vice-leader, CEC’s transport convenor and vice-convenor, and transport spokespersons from each party Continue reading

LCCC June 2019 meeting agenda

Monday, 17 June 2019
McDonald Road Library, Nelson Hall

 AGENDA

Continue reading