Tag Archives: roadworks

LCCC June minutes – final version

With apologies for delay, please click to download the approved minutes for LCCC’s June 2017 meeting: 2017_06_19 final.

Delay was due to

  1. The draft minutes could not be approved until LCCC met in August. (In common with many CCs, LCCC does not meet in July.)
  2. LCCC’s minutes secretary and web-weaver was unavailable for some of August and September due to personal and work commitments.

Leith Programme Stakeholder Update 109: Phase 4 (Iona Street to Brunswick Street)

(adapted from an email sent by Michael Motion of Turner & Townsend at 14:51 on 8 September. )

Dear Stakeholder

Our contractor, Crummock, returned to site as of Monday 4th September to remobilise for the completion of the Phase 4 scope of works. At that time, Brunswick Road was closed to accommodate the site compound, and will remain so until the works are completed. Iona Street was also closed to allow commencement of works to realign the kerb line, commence the road surfacing works including the raised table construction and to complete the pavement slabbing. It is likely this will take up to 3 weeks to complete, during which time Iona Street will remain closed.

In addition to the above, we are also working in the following areas:

  • Brunswick Street junction to complete the remain footpath slabbing to the S/E corner
  • Croall Place to complete the remaining Scottish Water rectification works, and to resolve surface water drainage issues
  • 2 nr road crossings on Leith Walk, north and south of Albert Street.

Continue reading

Leith Programme Stakeholder Update 107: Phase 4 (Iona Street to Brunswick Street)

 (adapted from an email from Michael Motion, Senior Project Manager at Turner & Townsend, sent at 16:51 on 21 August 2017)

As of Monday 4th September, following the Edinburgh festival embargo, our Contractor, Crummock, will be returning to Leith Walk to complete Phase 4 of the Leith Programme.  We anticipate completing these works by Friday 3rd November (being an 8 week construction programme).  Continue reading

LCCC August meeting agenda

Outline Agenda LCCC 21 August 2017

  1. Welcome, introductions, attendance and apologies
  2. Approval of Minutes of 19 June 2017 meeting
  3. Matters Arising
  4. Community Police Officer’s Report
  5. LCCC Office Bearers’ Reports
  6. Planning
  7. Transport
  8. Environment
  9. Councillors’ reports, MSPs’ reports, MP’s report
  10. Open Forum
  11. Bulletin
  12. AOCB
  13. Future Meetings (usually 3rd Monday of the month) and meeting topics/presentations

A detailed agenda will be available nearer the time.

Leith Programme Stakeholder Update 104: Phase 4 (Pilrig Street to McDonald Road) Weekly lookahead (w/c Monday 31st July 2017)

(adapted from an email sent by Steven Jackson of Turner & Townsend at 11:25 on 28 July. We apologise for the late posting of this news: our web-weaver was on holiday.)

Dear Stakeholder,

Following work completed to date we are targeting completing all pre embargo works and removing traffic management on Monday 31st July. Continue reading