Leith Programme Stakeholder Update 104: Phase 4 (Pilrig Street to McDonald Road) Weekly lookahead (w/c Monday 31st July 2017)

(adapted from an email sent by Steven Jackson of Turner & Townsend at 11:25 on 28 July. We apologise for the late posting of this news: our web-weaver was on holiday.)

Dear Stakeholder,

Following work completed to date we are targeting completing all pre embargo works and removing traffic management on Monday 31st July. Continue reading

Leith Programme Stakeholder Update 105: Phase 4 (Pilrig Street to McDonald Road) – Weekly lookahead (w/c Monday 31st July 2017)

(adapted from an email sent by Steven Jackson, Associate Director, Infrastructure, Turner & Townsend, at 11:25 on 2017_07_28)

Following work completed to date we are targeting completing all pre embargo works and removing traffic management on Monday 31st July. Continue reading

Leith Programme Stakeholder Update 104: Phase 4 (Pilrig Street to McDonald Road) Weekly lookahead (w/c Monday 24th July 2017)

(adapted from an email sent by Steven Jackson, Associate Director, Infrastructure, Turner & Townsend, at 14:57 on 2017_07_21)

 

With regards to the works and worksite locations for next week, these have been specified and set as the following:

  • Paving from Croall Place N/W corner to Shrub Place Lane set to continue and be completed by mid-next week.
  • Paving towards corner of Brunswick Street set to be completed on this coming Saturday (22nd July).
  • Taring of footway with corduroy paving slabs on Albert Place to begin next week and be completed by Friday 28th July.
  • Taring and slabbing of tactile paving set to begin next Tuesday on corner that meets Elm Row with Brunswick Street. To be finished by Friday 28th July.
  • Slabbing at bus stop shelter on Crighton Place to begin next week and be finished by Friday 28th July. Small section of slabbing on opposite side of the road also to be complete with regards to the same timeframe.
  • Traffic Management plan to be put in place next week allowing for completion of road markings at McDonald Road junction. Road markings to be finished Friday 28th July.
  • Road crossing islands (All three at McDonald Road junction and Albert Street junction) to be completed by Monday 24th July.
  • Taring and completion of curbing at Iona St as well as junction road markings to be done and completed on Friday 28th July.

Again, we remain on target to have completed our works, allowing the McDonald Road/Brunswick Road to re-open for the Edinburgh Festival embargo, and for all worksite boundary fencing to be removed off site, by the end of July.  For the safety of re-opening the junction, we are planning to do this as of Monday 31st July, as opposed to the previous Friday, 28th July.

Further to this, the demobilisation of the Iona Street compound will commence as of Monday 31st July, with the compound off site entirely by Friday 4th August.  At this time, the prohibition on entry to Iona Street from Leith Walk will be in place.

Should you have queries, or require any further information, in regards to the above, please do not hesitate to contact me direct or by using leith.programme@edinburgh.gov.uk.

Kind regards

Steven Jackson, Associate Director, Infrastructure, Turner & Townsend
Osborne House, 1 Osborne Terrace, Edinburgh, EH12 5HG
t: +44 (0) 131 347 3400 | m: +44 (0) 7764 443028 | www.turnerandtownsend.com

Leith Programme Stakeholder Update 103 – Phase 4 (Pilrig Street to McDonald Road) Weekly lookahead (w/c 17th July 2017)

(adapted from an email sent by Michael Motion, Senior Project Manager, Infrastructure, Turner & Townsend, at 16:06 on 2017_07_14)

Dear Stakeholder

With regards to the works and worksite locations for next week, these have been specified and set as the following:

  • Paving works will continue to the N/W corner on Croall Place (outside the Natwest Bank and towards Shrub Place Lane) and we hope to complete this area by the end of the week.
  • We are targeting completion of the footpath paving to Vittorias corner by tomorrow, 15th July.
  • Paving works will continue to the on Brunswick Street, and again we hope to have this complete this by the end of the week.
  • Road markings, necessary for the McDonald Road/Brunswick Road junction to open, began this week and will continue into next week

Again, we remain on target to have completed our works, allowing the McDonald Road/Brunswick Road to re-open for the Edinburgh Festival embargo, and for all worksite boundary fencing to be removed off site, by the end of July.  For the safety of re-opening the junction, we are planning to do this as of Monday 31st July, as opposed to the previous Friday, 28th July.

Further to this, the demobilisation of the Iona Street compound will commence as of Monday 31st July, with the compound off site entirely by Friday 4th August.  At this time, the prohibition on entry to Iona Street from Leith Walk will be in place.

Should you have queries, or require any further information, in regards to the above, please do not hesitate to contact me direct either at michael.motion@turntown.co.uk or at leith.programme@edinburgh.gov.uk.

Kind regards

Michael Motion

Senior Project Manager, Infrastructure, Turner & Townsend