Leith Programme Stakeholder Update 111 – Phase 4 (Iona Street to Brunswick Street)

(adapted from an email sent by Michael Motion, Senior Project Manager, Infrastructure, Turner & Townsend at 17:08 on 2017_09_22)

Completion of the road surfacing works will be noticeable as we complete areas and move the major worksites southwards towards McDonald Road and Brunswick Street. With that being the case, we will now be closing both McDonald Road and Brunswick Street junctions on Wednesday morning, 27th September with local diversions put in place. This will coincide with the opening up of both Iona Street and Albert Street. McDonald Road and Brunswick Street will remain closed until completion of all works by the end of October, as will Brunswick Road where the site compound is located. Continue reading

Leith Programme Stakeholder Update 110 – Phase 4 (Iona Street to Brunswick Street)

(adapted from an email from Michael Motion,  Senior Project Manager, Infrastructure, Turner & Townsend, sent at 11:31 on 2017_09_17)

Proposed works and worksite locations for w/c 18th September

  • Kerb realignment has been completed at the Iona Street junction, and the footpath slabbing works will progress this week
  • Completion of the footpath slabbing to the S/E corner of the Brunswick Street junction will continue this week
  • Continuing the Scottish Water works at Croall Place, followed by the footpath reinstatement works
  • Albert Street will close today for 2 weeks to accommodate the Leith Walk road re-surfacing works with associated traffic management and local diversions in place to accommodate these works
  • Road surfacing works are continuing north to south on Leith Walk, are progressing well, and will be focussed on the East side going past Albert Street this week

Continue reading

LCCC June minutes – final version

With apologies for delay, please click to download the approved minutes for LCCC’s June 2017 meeting: 2017_06_19 final.

Delay was due to

  1. The draft minutes could not be approved until LCCC met in August. (In common with many CCs, LCCC does not meet in July.)
  2. LCCC’s minutes secretary and web-weaver was unavailable for some of August and September due to personal and work commitments.

Leith Programme Stakeholder Update 109: Phase 4 (Iona Street to Brunswick Street)

(adapted from an email sent by Michael Motion of Turner & Townsend at 14:51 on 8 September. )

Dear Stakeholder

Our contractor, Crummock, returned to site as of Monday 4th September to remobilise for the completion of the Phase 4 scope of works. At that time, Brunswick Road was closed to accommodate the site compound, and will remain so until the works are completed. Iona Street was also closed to allow commencement of works to realign the kerb line, commence the road surfacing works including the raised table construction and to complete the pavement slabbing. It is likely this will take up to 3 weeks to complete, during which time Iona Street will remain closed.

In addition to the above, we are also working in the following areas:

  • Brunswick Street junction to complete the remain footpath slabbing to the S/E corner
  • Croall Place to complete the remaining Scottish Water rectification works, and to resolve surface water drainage issues
  • 2 nr road crossings on Leith Walk, north and south of Albert Street.

Continue reading

Leith Programme Stakeholder Update 107: Phase 4 (Iona Street to Brunswick Street)

 (adapted from an email from Michael Motion, Senior Project Manager at Turner & Townsend, sent at 16:51 on 21 August 2017)

As of Monday 4th September, following the Edinburgh festival embargo, our Contractor, Crummock, will be returning to Leith Walk to complete Phase 4 of the Leith Programme.  We anticipate completing these works by Friday 3rd November (being an 8 week construction programme).  Continue reading