(LCCC’s minutes secretary apologises for the late publication of these approved minutes. He was unable to attend the April meeting, and so his normal cycle was interrupted. However, there is no difference in content (apart from correcting a few punctuation errors) between the record below and the draft March minutes published here: https://leithcentralcc.co.uk/wp-content/uploads/2019/04/2019_03_18-draft-v1.pdf.)
Author Archives: minsec
NOTES of Meeting Community Council Together on Trams (CCTT) & Tram Team (TT) 25 April 2019
1. Welcome, introductions, minutes
- Present: Darren Wraight (DW), Jennifer Marlborough, Rob Levick, Angus Hardie, Charlotte Encombe, Andrew Mckenzie, Harald Tobermann (HT), Rob Leech (RL)
- Agreed: to ask Bruce Ryan to do future minutes (costs covered by Anturas)
2. Update TT team
a. Progress on CEC work on multi-year environmental cost/benefits post-tram
- Noted: this is being progressed by Hannah Ross (HR) who will advise
b. Confirmation of official ECI period (given the delayed mobilisation)
Noted: ECI is underway, but not all senior contractor staff are in Edinburgh. ECI will end 9 October 2019. Lane closures with heras and barrier will commence from 10 October 2019. To confirm the track slab design the contractor will carry out ground and site investigation along the route[note i]. This will be carried out via trail holes and bores. These works will be carried out under minor traffic management lasting on average 5 days per location.
- Noted: DW as ‘in-house’ stakeholder rep, and contractors are co-locating to 200 Bonnington Rd (200BR) for the period (perhaps beyond); other members of TT: HR (ca 1 day at 200BR) and RL (as required at 200BR) based at their respective main offices. New TT communication person is being recruited. Client team includes CEC tram team, Anturas, Turner Townsend, Atkins.
- Agreed: DW to provide diagram of all entities and key personnel involved and glossary of acronyms
- Noted: detailed trader logistics survey in progress; more info at next meeting
3. Update CCTT
- Noted: HT had meetings with Paul Lawrence, Hannah Ross and George Lowder to prepare the ground for CCTT/TT meetings during ECI period
- Noted: the role of the Traffic Management Review Panel (TMRP): includes representation of some but not all relevant groups (e.g. pedestrians and bus passengers – as opposed to bus operator – don’t have a dedicated voice)[note ii]
- Agree ‘shopping list’ (see below) priority, scope, input required, date decision required
- Agreed: see bold items in table below
4. Agree future meeting dates during ECI period
- Agreed: monthly meetings at 200BR on last THU, apart May (date tbc) and July (holiday[note iii]): 29 (tbc) May, 27 June, 29 August, 26 September; meetings beyond September TBA
- Agreed: due to pace of mobilisation, to meet contractors’ senior staff at June meeting
- Agreed: to keep an eye on Constitution Street fixing points and pre-works
Proposed Carriageway Resurfacing Works – Summer 2019/20
(adapted from an email from Edinburgh Council)
The carriageway on a number of streets in your Ward are due to be resurfaced during the Summer of 2019. The roads affected have been prioritised because of their current condition and because the upcoming tram works will prevent any planned resurfacing work from taking place in and around the proposed tram line during the construction period.
The resurfacing works are planned to start on 27 May and will be carried out during weekdays in separate phases in order to minimise disruption to the public. On some traffic sensitive routes, work may be carried out under nightshift to minimise the impact on traffic. Most roads affected will be fully or significantly resurfaced with a select few being only partially resurfaced or patched as required. There will also be some improvements to pedestrian facilities, traffic signal upgrades and renewal of some street furniture.
Leith Street closures: May and June 2019
(adapted from an email from Edinburgh Council, Nuveen and Laing O’Rourke, received 23 April 2019. LCCC’s webmaster apologises for the late posting of this information – work circumstances got in the way.)
Leith Street will close temporarily between the junction of Princes Street (Waterloo Place) and the turning into Calton Road. Laing O’Rourke would firstly like to say sorry that this was reported in the media before you heard the news from us. It was not able to share the news at that stage as the dates had not been confirmed.
The works will take place in two phases, with the road reopening in between:
PHASE ONE
Start date: 5 May 2019-19.00
End date: 25 May 2019 -0700
PHASE TWO
Start date: 6 June 2019-19.00
End date: 11 June 2019-0700 Continue reading
Research participants (still) wanted!
Do you use social media?
Do you have an older friend or relative that uses social media?
Do you help or support another adult to use social media?
Does someone help or support you to use social media?
If you answered YES to any of these questions, please consider taking 5 minutes to complete this short survey (https://survey.napier.ac.uk/n/smp.aspx) on how (and if) people help older adults to use social media.
This research is being undertaken at Edinburgh Napier University and is funded by the Carnegie Trust Foundation. (Estimated time commitment: 5 minutes.)
Also: Please do share on FB, Twitter, LinkedIn, or anywhere else, if you can!