Tag Archives: Planning

LCCC June minutes – final version

With apologies for delay, please click to download the approved minutes for LCCC’s June 2017 meeting: 2017_06_19 final.

Delay was due to

  1. The draft minutes could not be approved until LCCC met in August. (In common with many CCs, LCCC does not meet in July.)
  2. LCCC’s minutes secretary and web-weaver was unavailable for some of August and September due to personal and work commitments.

LCCC August meeting agenda

Outline Agenda LCCC 21 August 2017

  1. Welcome, introductions, attendance and apologies
  2. Approval of Minutes of 19 June 2017 meeting
  3. Matters Arising
  4. Community Police Officer’s Report
  5. LCCC Office Bearers’ Reports
  6. Planning
  7. Transport
  8. Environment
  9. Councillors’ reports, MSPs’ reports, MP’s report
  10. Open Forum
  11. Bulletin
  12. AOCB
  13. Future Meetings (usually 3rd Monday of the month) and meeting topics/presentations

A detailed agenda will be available nearer the time.

Stakeholder Update 101: Leith Programme – Phase 4 (Pilrig Street to McDonald Road) Weekly lookahead (w/c 3rd July 2017)

(adapted from an email from Michael Motion, Senior Project Manager, Infrastructure, Turner & Townsend)

With regards to works carried out this week, the contractor has not quite completed the paving works to the library corner, meaning the resource did not commence paving to the N/W corner at Croall Place. As such, we will be on site on Saturday to make-up some of the time lost this week due to the poor weather and to maintain our current programme of works.

In terms of works and worksite locations for next week, please see below:

  • Any final completion/grouting of paving at the library corner
  • Commence paving to the N/W corner on Croall Place West
  • Continue paving to Brunswick Street
  • Continue paving to Leith Walk East side
  • Complete crossing excavations and traffic signal duct installation at Brunswick Road
  • Return to complete duct crossings at the Albert Place pedestrian crossing (unfortunately the crossing will therefore be out of commission for a period of time next week) and just north of Shrub Place Lane

Continue reading

Leith Programme Stakeholder Update 100: Phase 4 (Pilrig Street to McDonald Road) weekly lookahead

(adapted from an email sent by Michael Motion, Senior Project Manager, Turner & Townsend on 23 June 2017 at 22:45)

Weekly lookahead (w/c 26th June 2017)

Please see below details of works to be undertaken during the course of next week, and the associated worksite locations during the course of next week:

  • Complete grouting to the slabbed paving at the Library corner and open up areas to pedestrians where safe to do so
  • Commence paving to the N/W corner of Croall Place (West side of Leith Walk)
  • Commence paving to Brunswick Street footpath at the junction with Leith Walk
  • Continue paving to the east side of Leith Walk
  • Kerb realignment, and commence kerb laying at Brunswick Street junction
  • Continue works to the road crossings at McDonald Road junction, excavating the tracks and installing ducts

165 Leith Walk – Former Tram Depot Demolition

The former tram depot, located at 165 Leith Walk, is due for demolition: further communication will follow regarding the programme for these works in the coming weeks. The area will be cleared and a creative workspaces project will occupy part of this site.

The smaller building at the front of the former depot (165a Leith Walk) will be retained and refurbished to create a pilot partnership hub delivering local services.  The project is a collaboration between site owners, The City of Edinburgh Council and local arts trust, Out of the Blue.

The project team intends to hold a drop-in community event on 28th June, between 4.30pm – 7.00pm, in the McDonald Road Library.  At this event, there will be an opportunity to find out more about these proposals and to ask any questions.

Should you have any queries or concerns with regards to the above, please do not hesitate to contact me direct either at this Email or at leith.programme@edinburgh.gov.uk

Kind regards

Michael Motion
Senior Project Manager, Infrastructure, Turner & Townsend