2-stage right-turns on Leith Walk: how they will work

(with thanks to Michael Motion for supplying the original diagram)

Click the thumbnails graphics to see the full-sized images.

Stage ‘0’: Cyclist arrives and waits at red sign Stage 1: Cycle signal turns green ahead of main signal, cyclist moves off. Cyclist moves to waiting area ahead of traffic, turns bike in the intended direction of travel, and waits at red signal.
Stage 2: Cycle signal turns green ahead of main signal. Cyclist moves off and continues journey original PDF

Upcoming Leith Creative reporting event: Leith Blueprint

(adapted from an email from Leith Creative)

Over the last six months, place-based research project Leith Creative has been engaging with Leithers, asking the simple question What would you do to make Leith better? Co-delivered by Morvern Cunningham (LeithLate) and Duncan Bremner (Citizen Curator), alongside creative partners BiomorphisHERE+NOW and Lateral North, Leith Creative has appeared at and facilitated 18 public engagement events in a six month timeframe, reaching over 2000 people who live and/or work in the Leith area.

Now Leith Creative like you to join them, as they feed back on the information they have gathered. The reporting event will take place in Custom Lane, a collaborative centre for design and making in the heart of the Leith community on Thursday 19th October between 6-8pm. Please reserve a place via Eventbrite. Continue reading

Leith Programme Stakeholder Update 114: Phase 4 (Iona Street to Brunswick Street)

(adapted from an email from Michael Motion, Senior Project Manager, Infrastructure, Leith Programme Project Team, sent on 2017_10_06 at 14:30)

This email contains information on

  • Proposed works w/c 9th October 2017
    • Road closures
    • Proposed works / worksite locations
  • Two-stage right turn for cyclists – junction of Leith Walk and McDonald Road/Brunswick Road
  • New segregated cycle lanes on Leith Walk
  • Picardy Place design update

Continue reading

Leith Programme Stakeholder Update 113 – Phase 4 (Iona Street to Brunswick Street)

(adapted from an email from Michael Motion, Senior Project Manager, Infrastructure, Leith Programme Project Team, sent at 11:01 on 2017_10_02)

Proposed works w/c 2nd October 2017

 Road closures

  • Albert Street (planned re-opening date Tuesday 10th October)
  • Brunswick Road (will remain closed until completion of the project at the end of October)
  • McDonald Road (will remain closed until completion of the project at the end of October)
  • Brunswick Street (planned re-opening date Wednesday 18th October 2017)

Continue reading

Leith Programme Stakeholder Update 112 – Tram to Newhaven & Leith Programme

(adapted from an email from Michael Motion, Senior Project Manager, Infrastructure, Leith Programme Project Team, on 2017_09_27 at 16:35)

Edinburgh Tram

As you may be aware, the Outline Business Case for taking trams to Newhaven was approved on the 21st of September by the City of Edinburgh Council.  You can see the Outline Business Case and the supporting report here under Reports and item 8·4.

A comprehensive tendering process will now get under way to secure a potential contractor partner for the project, with councillors due to make a final decision on taking the tram to Newhaven in autumn 2018 to allow construction to start in early 2019. Continue reading