The Engine Yard Development, Shrubhill: Work starting soon?
Allenbuild advise that
works at the Shrubhill former bus and tram depot will commence in late August 2016, with site-surveying and initial site clearance…. Piling works are scheduled to commence in late October 2016 and will last around 9 weeks, followed by below-ground foundations and the carpark structures. The superstructure of Block A on Leith Walk will commence early in 2017. The construction of the car park will be ongoing during 2017 with superstructure of the two blocks behind Block A both commencing later in 2017.
Fuller details are in this PDF. Continue reading