The walkway opened in the course of this week, following 18 months of lobbying CEC and pressing Miller Homes. Prior to that volunteers from the Water of Leith Trust had spent five days clearing the river and cutting back the overgrown vegetation. The path immediately behind Miller’s site is limited to circa 1m in width on a temporary basis while they continue with their protracted wall stabilisation works, but: the path is finally open. Gormley’s man who re-appeared nearly contemporaneously can be admired again mid-river, with some fine pieces of flotsam (or is it jetsam?) gathered behind him.
| Click the thumbnails to see the full-size photos. | |
Joint Community Council’s written submission regarding 106 – 162 Leith Walk, Edinburgh
Leith Central CC, Leith Harbour and Newhaven CC and Leith Links CC have published the following written submission: Joint Community Councils’ written submission
Traffic delays at Bonnington Toll
(adapted from an email from Edinburgh Council time-stamped 12:21 on 30 May [today].)
I write to provide an update with regards the traffic delays this week due to the work taking place at Bonnington Toll (as detailed below).
Over the past 2 days, a number of private vehicles parked close to the work area have made it difficult for large vehicles to pass the traffic management and as such this has extended journey times for commuters quite significantly at times.
However, as of this morning it has been managed to move all vehicles which were causing an obstruction and as a result journey times are significantly better this morning.
In addition, there have been some adjustments to the temporary traffic signal timings, to reflect the dynamic flows at the junction throughout the day. It is hoped that for the remainder of the work traffic queues and delays can remain as short as possible.
If you need to discuss this in any more detail or would like a further update, or have any concerns from residents, please do not hesitate to contact Steven Blacklaw. Please also CC secretary.lccc@leithcentralcc.co.uk
Steven Blacklaw ¦ Engineer – Transport Design & Delivery
Place ¦ Planning & Transport ¦ The City of Edinburgh Council
G4, Waverley Court, 4 East Market Street, Edinburgh EH8 8BG
Tel 0131 529 3252 steven.blacklaw@edinburgh.gov.uk
More detail on carriageway resurfacing works – Summer 2019/20
Following on from this post, Edinburgh Council has just sent the following detail about the road resurfacing planned for this summer.
| Location | Planned Start Date | Estimated Duration | Work Detail |
| Broughton Street | 28-May + 22 Aug | 4 weeks + 2 weeks | Pedestrian crossing upgrade + carriageway resurfacing |
| Albany Street | 03-Jun | 1 week | Carriageway resurfacing |
| Hopetoun Street | 07-Jun | 2 days | Carriageway resurfacing |
| Academy Street | 11-Jun | 1 week | Overlay setts |
| Dalmeny Street | 17-Jun | 10 days | Carriageway resurfacing, overlay setts and minor footway works |
| East Hermitage Place | 26-Jun | 3 days | Carriageway resurfacing |
| Portland Place | 28-Jun | 1 week | Carriageway resurfacing |
| McDonald Road | 01-Jul | 10 days | Footway widening and carriageway patching |
| Easter Road/Duke Street | 01-Jul | 8 weeks | Junction redesign |
| East London Street | 02-Jul | 7 weeks | Pedestrian crossing upgrade and carriageway resurfacing |
| Duncan Place | 10-Jul | 2 weeks | Carriageway resurfacing and minor footway works |
| Great Junction Street | 10-Jul | 1 week | Carriageway resurfacing |
| Gordon Street | 02-Aug | 1 week | Carriageway resurfacing |
| Bonnington Road | 08-Aug | 3 weeks | Carriageway resurfacing |
| Ocean Drive | 08-Aug | 3 days | Carriageway resurfacing |
| North Leith Sands | 13-Aug | 1 week | Carriageway resurfacing and minor footway works |
| Newhaven Road | 26-Aug | 2 weeks | Carriageway resurfacing |
| Annandale Street | 29-Aug | 7 weeks | New pedestrian crossings and carriageway resurfacing |
| Broughton Road | 05-Sep | 2 weeks | Carriageway resurfacing |
| Easter Road | 11-Sep | 3 weeks | Carriageway resurfacing and minor footway works |
| Links Place | 23-Sep | 4 weeks | Carriageway resurfacing, new traffic island and footway works |
| Pilrig Street | 29-Sep | 4 weeks | Carriageway resurfacing, new traffic island and footway works |