Leith Programme Stakeholder Update 115: Phase 4 (Iona Street to Brunswick Street)

(adapted from an email from Michael Motion, of Leith Programme Project Team, sent at 14:55 on 2017_10_27. Mr Motion has confirmed that updates were not sent on 2017_10_13 and 2017_10_20.)

To confirm that the segregated cycleway, including the bus stop bypasses, and the 2-stage right turn for cyclists at the McDonald Road/Brunswick Road junction were opened for use on Wednesday 25th October.

As of next week, w/c 30th October, the contractor will be visible on site as they make good any defective works, within remote worksites.  Any impact on pedestrians and cyclists will be kept to an absolute minimum.

There will also be works carried out next week to replace the bus shelter at Albert Street and install the bus tracker at this location.  Unfortunately, we were unable to coordinate the sub-contractor to complete these works earlier, and so there will be an impact on the cycleway at this location which, again, we will try to keep to a minimum and ensure that the route is maintained.

Finally, there has been a small site compound set up within the parking bays at Albert Street to accommodate the contractor while it completes remaining works, which we anticipate will be for around 3-4 weeks. Continue reading

Edinburgh flat residents – what do you think of on street recycling bins?

(adapted from an email from Changeworks)

If you live in a flat in Edinburgh, Changeworks would like to ask your views of the shared waste and recycling bins on your street. The results of this survey will help the City of Edinburgh Council improve the service. The short online survey, which only takes 5-10 minutes to complete, is available to Edinburgh residents until 23 October 2017.

By taking part in the survey, you can enter a prize draw* with the chance to win several prizes including vouchers for Pizza Express and Cineworld, and family passes to the Camera Obscura in Edinburgh. You will also be offered the chance to attend a paid focus group, scheduled for November 2017, where feedback and ideas will be explored in more depth.

You can also follow @ChangeworksUK on Facebook and Twitter to share and retweet their posts about the recycling survey.

*Terms and conditions apply

2-stage right-turns on Leith Walk: how they will work

(with thanks to Michael Motion for supplying the original diagram)

Click the thumbnails graphics to see the full-sized images.

Stage ‘0’: Cyclist arrives and waits at red sign Stage 1: Cycle signal turns green ahead of main signal, cyclist moves off. Cyclist moves to waiting area ahead of traffic, turns bike in the intended direction of travel, and waits at red signal.
Stage 2: Cycle signal turns green ahead of main signal. Cyclist moves off and continues journey original PDF

Upcoming Leith Creative reporting event: Leith Blueprint

(adapted from an email from Leith Creative)

Over the last six months, place-based research project Leith Creative has been engaging with Leithers, asking the simple question What would you do to make Leith better? Co-delivered by Morvern Cunningham (LeithLate) and Duncan Bremner (Citizen Curator), alongside creative partners BiomorphisHERE+NOW and Lateral North, Leith Creative has appeared at and facilitated 18 public engagement events in a six month timeframe, reaching over 2000 people who live and/or work in the Leith area.

Now Leith Creative like you to join them, as they feed back on the information they have gathered. The reporting event will take place in Custom Lane, a collaborative centre for design and making in the heart of the Leith community on Thursday 19th October between 6-8pm. Please reserve a place via Eventbrite. Continue reading

Leith Programme Stakeholder Update 114: Phase 4 (Iona Street to Brunswick Street)

(adapted from an email from Michael Motion, Senior Project Manager, Infrastructure, Leith Programme Project Team, sent on 2017_10_06 at 14:30)

This email contains information on

  • Proposed works w/c 9th October 2017
    • Road closures
    • Proposed works / worksite locations
  • Two-stage right turn for cyclists – junction of Leith Walk and McDonald Road/Brunswick Road
  • New segregated cycle lanes on Leith Walk
  • Picardy Place design update

Continue reading