Leith Programme Stakeholder Update 81 – Pilrig Street to McDonald Road

(adapted from an email from Anna Herriman, Partnership and Information Manager, sent on 14 December 2015 at 09:53)

Council Report and Leith Programme Phase 4

At last Thursday’s meeting of the City of Edinburgh Council, a report ‘Edinburgh Tram Extension – Next Steps’ was considered. Whilst a report on the proposed tram extension to Newhaven is due to be considered in Spring/Summer 2017, it was agreed that in the meantime, preparatory ‘enabling’ work will be carried out as an integrated part of the Leith Programme. This will avoid unnecessary future duplication of work, should the extension go ahead.  Council also agreed to merge the Tram and Leith Programme projects from this point forward.  The two projects will now develop a programme for the delivery of Phase 4 (Pilrig Street to McDonald Road) including enabling works, and confirm this to you in due course. Please look out for further email updates from us in early 2016.

Continue reading

Roseburn to Leith Walk cycle link: deadline extended

(adapted form an email from Edinburgh Council)

Following initial consultation regarding the Roseburn to Leith cycle link and street improvements it has been agreed that there should be an extension on the period for reply.

The period for responding has been extended until 1 February 2016.

Thank you to those that have already responded. Further comments can continue to be submitted by email to cyclingprojects.consultation@edinburgh.gov.uk  or via the online survey at the website www.edinburgh.gov.uk/roseburntoleith

Allan Hutcheon I Professional Officer I Projects Development I Transport I Services for Communities I City of Edinburgh Council I Waverley Court, 4 East Market Street, Edinburgh, EH8 8BG I 0131 469 3672 I allan.hutcheon@edinburgh.gov.uk

 

Boundary Changes between Silverfields site and Pilrig Park

LCCC has received the following drawings and information from the developer via Friends of Pilrig Park.

Click the thumbnail images to open full-sized PDFs:

S:TechnicalPROJECTSCurrentEdinburgh - SilverfieldsArchitects4 - Site LayoutA 02 01 L A02 01 L (1)

A 02 01 M

S:TechnicalPROJECTSCurrentEdinburgh - SilverfieldsArchitects5 - Site Specific House-typesPlanningBoundary TreatmentsB

Boundary Treatments A09 01

C:UsersfbradyDesktopE10195~1001_1_J A3 (1)

Footpath temporary measures plan

Proposed Signage Location Plan

Proposed Signage Location Plan

S:TechnicalPROJECTSCurrentEdinburgh - SilverfieldsEngineers9. Inhouse DesignsSK1 Footpath Remedials A0 (1)

SK1 Footpath Remedials

streetlight brochure

streetlight brochure

Continue reading