I write to provide an update to my ongoing carriageway resurfacing programme in and around Leith prior to the commencement of the work to extend the tram to Newhaven.

Works on site at Pilrig Street junction, Dalmeny Street and East London Street are due to complete at the end of next week (Friday 12 July) after which time the main contractor has a company recess for 2 weeks.

On returning to site on the 29 July, the work to redesign the junction at Duke Street and Easter Road will fully commence (some preparatory work will take place next week) while the majority of work ongoing elsewhere will be predominantly carriageway resurfacing work.

To this effect, please find below a basic table detailing the proposed locations, dates and traffic management for the resurfacing work and I have also attached the full programme in the form of a Gantt chart. I will caveat this and remind everyone that dates are approximate as any delays can have a knock on effect, however the order of work should remain the same and I will update EdinTravel as works progress.

I will also explain that the programme has extended due to additional work being requested and some issues on site with traffic signal installations however the main resurfacing work should throw up little in the way of unforeseen delays and there will be no further additional work included in the programme unless it is deemed important and we create space in the existing programme. We also remain in full contact with the team leading the Tram extension with regards their preparatory work and start date.

As before, residents and traders will receive notices prior to the start of work in their area with more specific details, and I will forward a copy of these notices on as appropriate. If you have any queries or concerns, please do not hesitate to contact me.

Month Date (Duration) Location Time Proposed Traffic Management
July 9 (2 days) East London Street Day Road Closure
29 (7 days) North Leith Sands Day Road Closure
29 (35 days) Duke Street R’about Redesign Day Retain roundabout as long as possible
August 7 (5 days) Great Junction Street Day Southbound loop using Henderson?
7 (9 days) Duncan Place Day Road Closure
8 (21 days) Links Place Traffic Islands Day Road Narrowing
15 (4 days) Gordon Street Day Road Closure
20 (3 days) Ocean Drive Day Road Closure.1 side at a time.
20 (12 days) Pilrig Street Day Road Closure in 2 phases
26 (6 days) Annandale Street Day Road Closure
September 2 (12 days) Bonnington Road Night Road Closure in 2 phases
9 (5 days) Broughton Street Night Road Closure
18 (12 days) Newhaven Road Night Road Closure in 2 phases
20 (21 days) Easter Road Night Phased road closures, road narrowing
October 10 (12 days) Broughton Road Night Road Closure in 2 phases
17 (2 days) East Hermitage Pl Junction Night 3 phase TTL’s – Close Links Gdns
28 (5 days) Portland Place Night Eastbound Closure using Ocean Drive
28 (10 days) Links Place Night Road Closure in 2 phases
November 4 (6 days) Academy Street Night Road closure, Duke St eastbound closure

Kind regards

Steven Blacklaw ¦ Engineer – Transport Design & Delivery
Place ¦ Planning & Transport ¦ The City of Edinburgh Council ¦ G4, Waverley Court, 4 East Market Street, Edinburgh EH8 8BG
Tel 0131 529 3252 steven.blacklaw@edinburgh.gov.uk

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

This site uses Akismet to reduce spam. Learn how your comment data is processed.