Stakeholder Update 116 – Leith Programme – Phase 4

(adapted from an email from Michael Motion of Leith Programme Project Team, sent at 11:54 on 2017_11_23)

In our last communication (27th October) we explained that the Contractor would be commencing the making good of defective works within remote worksites on Leith Walk.  This work is progressing well and we have taken the opportunity to also make good some defects in the work carried out during Phase 2 of the Leith Programme between the Foot of the Walk and Dalmeny Street.

Our current programme is as follows:

  • Replace bus shelter and install bus tracker at Albert Street – Complete
  • Phase 2 remedial works as above – Due to complete by 24th November
  • Make good surfacing to the southbound bus stop bypass at Shrubhill – Due to complete by 1st December
  • Resolve ponding issue to Brunswick Street cycleway – Due to complete by 1st December
  • Remove temporary footway ramps at Iona Street and Albert Street – Due to complete by 1st December
  • General making good works to kerbs and road/footway chambers – Due to complete by 1st December

Thank you for bearing with us as we complete these works.

Should you require any further information, please do not hesitate to contact the Leith Programme Email address: leith.programme@edinburgh.gov.uk