Tag Archives: roadworks

Stakeholder Update 86 – Leith Programme Phase 4 – Works update for week commencing 12 September

(adapted from an email sent by Alan Dean, Partnership Development Officer, sent on 2016_09_09 at 15:49)

Leith Programme Phase 4 (Pilrig Street to McDonald Road)

Following their site mobilisation and initial preparatory works this week, Land Engineering Ltd, the contractors appointed to deliver the Pilrig Street to McDonald Road section of our improvement works, will commence construction next week (12 September 2016) adjacent to the Shrubhill redevelopment site and Middlefield on the west side of Leith Walk. These works will concentrate on footway reconstruction. The traffic management will consist of a single lane closure in order to ensure minimal disruption and traffic flow. Continue reading

Stakeholder Update 84 – Leith Programme Phase 4 (Pilrig Street to McDonald Road)

(adapted from an email sent by Alan Dean, Partnership Development Officer, sent on 2016_08_04 at 15:08)

Appointment of contractor announcement

Following the conclusion of the procurement process for Phase 4 of the Leith Programme, we are pleased to announce that the contractor who will be responsible for delivering the Pilrig Street to McDonald Road section of our improvement works will be Land Engineering Ltd. It is planned that they will mobilise on site in late August to allow construction to start in September 2016. As previously highlighted, it is anticipated that the works will last around 10 months with a planned completion date expected in Summer 2017. More details will follow in a future update. Continue reading

Stakeholder Update 83 – Leith Programme Phase 4 (Pilrig Street to McDonald Road)

(adapted from an email sent by Alan Dean, Partnership Development Officer, sent on 2016_07_05 at 10:05)

Anticipated timescales

We would like to let you know that we are on course to commence the next phase of the Leith Programme works this Summer as previously reported in our last stakeholder update. Following the Council’s approving of the making of the Traffic Regulation Order (TRO) and Redetermination Order (RSO) at the Transport and Environment Committee of 7th June 2016, the team have been working hard to complete the procurement process to appoint the contractor for the forthcoming section of works and we are confident that work will start in late August/early September. Once we have selected the successful contractor we will, of course, share this with you and will carry out a large scale letter drop over the wider area to ensure people are kept fully informed. It is anticipated that the works will take around 10 months to complete. Continue reading