Final piling at Shrubhill

(adapted from an email from Allenbuild, received 6 March 2018)

If you have any concerns about the following, please contact Donald McLean of Allenbuild directly. Please also CC your concerns to planning.lccc@leithcentralcc.co.uk.

The final piling ‘visit’ to the Shrubhill site, which stretches from Leith Walk to Dryden St is going ahead. Piling equipment will mobilise to site on Monday 12 March. The duration of the piling should be no more than 3 weeks.

  • The first week’s work will be taking place alongside the railway track beside the old chimney.
  • The middle week will be the works to the two buildings nearest the old gable walls on the boundary.
  • The final week back into the middle of the site.

Allenbuild will position vibration-monitoring equipment along the old gables and at the rail bridge and chimney.

No piling will commence before 08:00 am. Piling will cease by 18:30. It is likely that piling will also occur on Saturday 17 March and Saturday 24 March, from 08:00 to 14:30 at the latest.

Donald McLean, Project Manager, Allenbuild Ltd

The Engine Yard, 28 Dryden Street, Edinburgh, EH7 4PW
Site Office: 0131 478 1246 ext 202.          Mobile: 07484 039 677
Email: donald.mclean@placesforpeople.co.uk

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google+ photo

You are commenting using your Google+ account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

This site uses Akismet to reduce spam. Learn how your comment data is processed.