(Please note that this statement was circulated by Alan Dean, CEC Partnership Development Officer (Stakeholder Liaison and Engagement) on 2 April 2015 at 15:40
Leith Programme Stakeholder Update 70
The Foot of the Walk junction works:
The contractors carrying out the upgrade works to the Foot of the Walk junction (MacLay Civil Engineering Ltd) are making good progress with the current work sections.
- Crown Place to Duke Street – Slabbing completed
- Duke Street south side – Slabbing completed
- Constitution Street/Duke Street corner area and Duke Street north side – Anticipated completion date Friday 3 April
Work is continuing on the re-paving of the public realm space in front of the Kirkgate Shopping Centre with a significant part of the main area now completed.