Tag Archives: Leith Walk

Leith Walk patching: earlier updates

 The following information is emailed updates, preceding week 4 patching updatesent from a CEC official to Cllr Nick Gardner (t. 0131 529 3282; email Nick.Gardner@edinburgh.gov.uk), who then kindly forwarded them to LCCC. The text of these emails is unchanged apart from making links to TTROs etc attached to the emails, and redacting the CEC official’s name and contact details. Any comments should be sent to Alan Dean of CEC – but please email LCCC a copy

Alan Dean BA (Hons) MSc | Project Officer (Leith Programme/Tram Enabling) | Place Directorate | City Centre Leith Neighbourhood Team | 249 High Street | Edinburgh | EH1 1PN
Tel: 0131 529 7519        Mobile: 07739 188 438        alan.dean@edinburgh.gov.uk

Continue reading

Leith Walk patching update – Week 4

The following information has been provided via Cllr Nick Gardner (t. 0131 529 3282; e. Nick.Gardner@edinburgh.gov.uk) by CEC’s Transport Design and Delivery section within Traffic & Engineering Services. At this point it is not clear whether the contract will complete for both north- and south-bound carriageways between Brunswick and Picardy by 7 December, as stated in CEC’s stakeholder communication 90 of 21 October 2016

This is the fourth update on the patching works for Leith Walk which started on Sunday 23rd October 2016.

Works have progressed well again this week with the contractor safely negotiating the difficult works at the London Road Roundabout which has inevitably slowed progress down due to the requirement to reset various pieces of ironwork and carry out trial holes and plane the carriageway in two layers to ensure they avoided coming into contact with the London Road Air Raid shelter located on the west side of Antigua Street and under the roundabout itself.

The programme is still ahead of schedule and has now completed sections 6, 7, 5 and 4 (London Road to Annandale Street) and will commence section 3 tomorrow night (Thursday 10/11).

As part of the ongoing management process of patching contracts such as this we are currently assessing the remainder of the works to ensure best value is achieved and whether alternative methods would be better suited to complete the works. I will be in a better position to provide an update on this by next week’s update.

Next week, and in line with previous week’s timings, operations will start at 7.00pm on the evening of Sunday 13th November on the south bound carriageway from Montgomery Street to London Road and continue through to Thursday 17th November including a newly identified section on Leopold Place.

Again, all noisy operations (jackhammers, planers etc.) will be completed by 10.00 o’clock and all operations concluding by 2.00am at the latest.

As ever, please be assured that every effort is continuing to be made complete these works as soon as practicable.

Stakeholder Update 91: Drop-in Surgery Invitation and Pilrig Street Junction Upgrade Latest

Adapted from an email sent by Alan Dean, Partnership Development Officer, sent on 2016_10_26 at 16:48.

Leith Central CC wishes to highlight the major delay to Pilrig St junction improvements – work will now not start until JANUARY 2017.  Continue reading

Leith Programme Stakeholder Update 90 – Various

Adapted from an email sent by Alan Dean, Partnership Development Officer, sent on 2016_10_19 at 16:31.

Annotations (in footnotes) are by Harald Tobermann, LCCC’s stakeholder representative for Leith Walk works.

I have set out below an update for the various projects currently underway. It is worth emphasising that the consultation period for the Phase 5 Traffic Regulation Order (Brunswick Street to Montgomery Street) is being extended and details of this are also set out below. Continue reading