Tag Archives: Pilrig St

Stakeholder Update 91: Drop-in Surgery Invitation and Pilrig Street Junction Upgrade Latest

Adapted from an email sent by Alan Dean, Partnership Development Officer, sent on 2016_10_26 at 16:48.

Leith Central CC wishes to highlight the major delay to Pilrig St junction improvements – work will now not start until JANUARY 2017.  Continue reading

Leith Programme Stakeholder Update 90 – Various

Adapted from an email sent by Alan Dean, Partnership Development Officer, sent on 2016_10_19 at 16:31.

Annotations (in footnotes) are by Harald Tobermann, LCCC’s stakeholder representative for Leith Walk works.

I have set out below an update for the various projects currently underway. It is worth emphasising that the consultation period for the Phase 5 Traffic Regulation Order (Brunswick Street to Montgomery Street) is being extended and details of this are also set out below. Continue reading

Stakeholder Update 82 – Leith Programme Phase 4 (Pilrig Street to McDonald Road): Anticipated Timescale 2016

(Adapted from an email from Alan Dean, Partnership Development Officer, sent on 2016_02_12 at 14:16)

We would like to inform you that the initial stages of the procurement process for appointing a contractor to carry out the next phase of the Leith Programme works are underway. It is planned that contractors will mobilise on site to allow construction to start after the Edinburgh Festival in summer 2016. At this stage, it is anticipated that the works will take around 10 months to complete. Continue reading