Leith Walk works: informal drop-in event on Wednesday 14th June

(adapted from an email from Michael Motion, Senior Project Manager, Infrastructure, Turner & Townsend)

Further to the events of last week, in regards to the administration of the previous Leith Programme Phase 4 Contractor, and the re-commencement of works on Monday 5th June, we intend to hold an informal drop-in event on Wednesday 14th June, commencing from 5pm – 7pm to provide any further information we can regarding the current contractor situation, the progress on site and to answer any general queries with regards to the Leith Programme Phase 4 project.

This will be held within the Learning Centre room at the McDonald Road Library.

We hope to see you there.

Kind regards

Michael Motion
Senior Project Manager, Infrastructure, Turner & Townsend

Shrub Place construction: hear all about it!

What?

Presentation on Shrub Place site construction plans and timetable; impact/s on neighbours and the Leith Walk road works by Mike Henderson, Senior Project Manager, Places for People, followed by Q&A

When?

Monday June 19th, as part of Leith Central CC’s monthly meeting – all welcome!

Where?

McDonald Road Library, 2-4 McDonald Rd, Edinburgh EH7 4LU

Leith Programme Stakeholder Update 97: Phase 4 (Pilrig Street to McDonald Road)

(adapted from an email from Michael Motion, Senior Project Manager, Infrastructure, Turner & Townsend at 12:19 on 2017_06_02. 

Having received the latest update, LCCC has sought confirmation that Crummock will be using the compound in Iona Street and the stock stored there. This would make it easier to continue works already underway and save time ordering stock.

We also asked whether the sub-contractor who looks after Phase 4 traffic signage will work under Crummock’s direction and deal with current signage (and fencing/barrier) issues today. 

We will relay any answers as we receive them.)

Dear Stakeholder

We refer to our communication yesterday regarding the Leith Programme contractor being put into administration.

We have now completed an options appraisal and identified an interim way forward that will ensure work re-commences on Monday 5th June. The works will be carried out by a Council framework contractor, Crummock (Scotland) Limited, and will concentrate, in the first instance, in the work sites that are currently partially complete.

As you will appreciate, we are dealing with a complex situation but feel we have reacted as quickly as possible to maintain momentum on the project. We will of course keep you updated as more detailed plans emerge.

Thank you for patience in this matter.

Regards

Michael Motion