Trams to Newhaven: timeline

(Dates taken from an email sent by Rory Garriock, Communications and Marketing Manager, Anturas Consulting Ltd)

item date
Tenders out 20/04/2018
Analysis of consultation responses May 2018
Community Workshops 2nd half of June
Tenders returned End of July 2018
Design changes July – August 2018
Engagement 2 Early September 2018
Preferred bidder selected November 2018
Vote of full Council End November/start December 2018
Engagement impact report January 2019
Enabtdng works commence on Leith Walk Spring 2019, followed directly by infrastructure works
London Road to Manderston Street expected completion Winter 2020
Manderston Street to Duke Street expected completion Summer 2021

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google+ photo

You are commenting using your Google+ account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

w

Connecting to %s

This site uses Akismet to reduce spam. Learn how your comment data is processed.