(Dates taken from an email sent by Rory Garriock, Communications and Marketing Manager, Anturas Consulting Ltd)
item | date |
Tenders out | 20/04/2018 |
Analysis of consultation responses | May 2018 |
Community Workshops | 2nd half of June |
Tenders returned | End of July 2018 |
Design changes | July – August 2018 |
Engagement 2 | Early September 2018 |
Preferred bidder selected | November 2018 |
Vote of full Council | End November/start December 2018 |
Engagement impact report | January 2019 |
Enabtdng works commence on Leith Walk | Spring 2019, followed directly by infrastructure works |
London Road to Manderston Street expected completion | Winter 2020 |
Manderston Street to Duke Street expected completion | Summer 2021 |