(Dates taken from an email sent by Rory Garriock, Communications and Marketing Manager, Anturas Consulting Ltd)
| item | date |
| Tenders out | 20/04/2018 |
| Analysis of consultation responses | May 2018 |
| Community Workshops | 2nd half of June |
| Tenders returned | End of July 2018 |
| Design changes | July – August 2018 |
| Engagement 2 | Early September 2018 |
| Preferred bidder selected | November 2018 |
| Vote of full Council | End November/start December 2018 |
| Engagement impact report | January 2019 |
| Enabtdng works commence on Leith Walk | Spring 2019, followed directly by infrastructure works |
| London Road to Manderston Street expected completion | Winter 2020 |
| Manderston Street to Duke Street expected completion | Summer 2021 |