Tag Archives: Bernard St

Leith Programme Stakeholder Update 90 – Various

Adapted from an email sent by Alan Dean, Partnership Development Officer, sent on 2016_10_19 at 16:31.

Annotations (in footnotes) are by Harald Tobermann, LCCC’s stakeholder representative for Leith Walk works.

I have set out below an update for the various projects currently underway. It is worth emphasising that the consultation period for the Phase 5 Traffic Regulation Order (Brunswick Street to Montgomery Street) is being extended and details of this are also set out below. Continue reading

Stakeholder Update 85 – Leith Programme Phase 4 contractor mobilisation reminder, and Bernard Street survey work

(adapted from an email sent by Anna Herriman, Acting City Centre Programme Manager, sent on 2016_09_02 at 13:55)

Leith Programme Phase 4 (Pilrig Street to McDonald Road) contractor mobilisation on site

A reminder that following the procurement process for Phase 4 of the Leith Programme, Land Engineering Ltd was appointed to deliver the Pilrig Street to McDonald Road section of our improvement works. Land Engineering are currently mobilising on site, ahead of a 10 month construction period due to start in September 2016, with a planned completion date expected in Summer 2017.

In addition, in advance of the Council deciding on whether or not to extend the tram line north of York Place, enabling works will be incorporated in the footways in order to ensure that, should the decision be taken in 2017 to extend the current line, future disruption impacting on the local area is kept to a minimum. Continue reading