Leith Programme Stakeholder Update 100: Phase 4 (Pilrig Street to McDonald Road) weekly lookahead

(adapted from an email sent by Michael Motion, Senior Project Manager, Turner & Townsend on 23 June 2017 at 22:45)

Weekly lookahead (w/c 26th June 2017)

Please see below details of works to be undertaken during the course of next week, and the associated worksite locations during the course of next week:

  • Complete grouting to the slabbed paving at the Library corner and open up areas to pedestrians where safe to do so
  • Commence paving to the N/W corner of Croall Place (West side of Leith Walk)
  • Commence paving to Brunswick Street footpath at the junction with Leith Walk
  • Continue paving to the east side of Leith Walk
  • Kerb realignment, and commence kerb laying at Brunswick Street junction
  • Continue works to the road crossings at McDonald Road junction, excavating the tracks and installing ducts

165 Leith Walk – Former Tram Depot Demolition

The former tram depot, located at 165 Leith Walk, is due for demolition: further communication will follow regarding the programme for these works in the coming weeks. The area will be cleared and a creative workspaces project will occupy part of this site.

The smaller building at the front of the former depot (165a Leith Walk) will be retained and refurbished to create a pilot partnership hub delivering local services.  The project is a collaboration between site owners, The City of Edinburgh Council and local arts trust, Out of the Blue.

The project team intends to hold a drop-in community event on 28th June, between 4.30pm – 7.00pm, in the McDonald Road Library.  At this event, there will be an opportunity to find out more about these proposals and to ask any questions.

Should you have any queries or concerns with regards to the above, please do not hesitate to contact me direct either at this Email or at leith.programme@edinburgh.gov.uk

Kind regards

Michael Motion
Senior Project Manager, Infrastructure, Turner & Townsend

Stakeholder Update 82 – Leith Programme Phase 4 (Pilrig Street to McDonald Road): Anticipated Timescale 2016

(Adapted from an email from Alan Dean, Partnership Development Officer, sent on 2016_02_12 at 14:16)

We would like to inform you that the initial stages of the procurement process for appointing a contractor to carry out the next phase of the Leith Programme works are underway. It is planned that contractors will mobilise on site to allow construction to start after the Edinburgh Festival in summer 2016. At this stage, it is anticipated that the works will take around 10 months to complete. Continue reading