Leith Programme Stakeholder Update 114: Phase 4 (Iona Street to Brunswick Street)

(adapted from an email from Michael Motion, Senior Project Manager, Infrastructure, Leith Programme Project Team, sent on 2017_10_06 at 14:30)

This email contains information on

  • Proposed works w/c 9th October 2017
    • Road closures
    • Proposed works / worksite locations
  • Two-stage right turn for cyclists – junction of Leith Walk and McDonald Road/Brunswick Road
  • New segregated cycle lanes on Leith Walk
  • Picardy Place design update

Continue reading

Leith Programme Stakeholder Update 113 – Phase 4 (Iona Street to Brunswick Street)

(adapted from an email from Michael Motion, Senior Project Manager, Infrastructure, Leith Programme Project Team, sent at 11:01 on 2017_10_02)

Proposed works w/c 2nd October 2017

 Road closures

  • Albert Street (planned re-opening date Tuesday 10th October)
  • Brunswick Road (will remain closed until completion of the project at the end of October)
  • McDonald Road (will remain closed until completion of the project at the end of October)
  • Brunswick Street (planned re-opening date Wednesday 18th October 2017)

Continue reading

Leith Programme Stakeholder Update 112 – Tram to Newhaven & Leith Programme

(adapted from an email from Michael Motion, Senior Project Manager, Infrastructure, Leith Programme Project Team, on 2017_09_27 at 16:35)

Edinburgh Tram

As you may be aware, the Outline Business Case for taking trams to Newhaven was approved on the 21st of September by the City of Edinburgh Council.  You can see the Outline Business Case and the supporting report here under Reports and item 8·4.

A comprehensive tendering process will now get under way to secure a potential contractor partner for the project, with councillors due to make a final decision on taking the tram to Newhaven in autumn 2018 to allow construction to start in early 2019. Continue reading

Leith Programme Stakeholder Update 111 – Phase 4 (Iona Street to Brunswick Street)

(adapted from an email sent by Michael Motion, Senior Project Manager, Infrastructure, Turner & Townsend at 17:08 on 2017_09_22)

Completion of the road surfacing works will be noticeable as we complete areas and move the major worksites southwards towards McDonald Road and Brunswick Street. With that being the case, we will now be closing both McDonald Road and Brunswick Street junctions on Wednesday morning, 27th September with local diversions put in place. This will coincide with the opening up of both Iona Street and Albert Street. McDonald Road and Brunswick Street will remain closed until completion of all works by the end of October, as will Brunswick Road where the site compound is located. Continue reading

LCCC June minutes – final version

With apologies for delay, please click to download the approved minutes for LCCC’s June 2017 meeting: 2017_06_19 final.

Delay was due to

  1. The draft minutes could not be approved until LCCC met in August. (In common with many CCs, LCCC does not meet in July.)
  2. LCCC’s minutes secretary and web-weaver was unavailable for some of August and September due to personal and work commitments.

Leith Programme Stakeholder Update 107: Phase 4 (Iona Street to Brunswick Street)

 (adapted from an email from Michael Motion, Senior Project Manager at Turner & Townsend, sent at 16:51 on 21 August 2017)

As of Monday 4th September, following the Edinburgh festival embargo, our Contractor, Crummock, will be returning to Leith Walk to complete Phase 4 of the Leith Programme.  We anticipate completing these works by Friday 3rd November (being an 8 week construction programme).  Continue reading