Leith Programme Stakeholder Update 115: Phase 4 (Iona Street to Brunswick Street)

(adapted from an email from Michael Motion, of Leith Programme Project Team, sent at 14:55 on 2017_10_27. Mr Motion has confirmed that updates were not sent on 2017_10_13 and 2017_10_20.)

To confirm that the segregated cycleway, including the bus stop bypasses, and the 2-stage right turn for cyclists at the McDonald Road/Brunswick Road junction were opened for use on Wednesday 25th October.

As of next week, w/c 30th October, the contractor will be visible on site as they make good any defective works, within remote worksites.  Any impact on pedestrians and cyclists will be kept to an absolute minimum.

There will also be works carried out next week to replace the bus shelter at Albert Street and install the bus tracker at this location.  Unfortunately, we were unable to coordinate the sub-contractor to complete these works earlier, and so there will be an impact on the cycleway at this location which, again, we will try to keep to a minimum and ensure that the route is maintained.

Finally, there has been a small site compound set up within the parking bays at Albert Street to accommodate the contractor while it completes remaining works, which we anticipate will be for around 3-4 weeks. Continue reading

Leith Programme Stakeholder Update 114: Phase 4 (Iona Street to Brunswick Street)

(adapted from an email from Michael Motion, Senior Project Manager, Infrastructure, Leith Programme Project Team, sent on 2017_10_06 at 14:30)

This email contains information on

  • Proposed works w/c 9th October 2017
    • Road closures
    • Proposed works / worksite locations
  • Two-stage right turn for cyclists – junction of Leith Walk and McDonald Road/Brunswick Road
  • New segregated cycle lanes on Leith Walk
  • Picardy Place design update

Continue reading

Leith Programme Stakeholder Update 113 – Phase 4 (Iona Street to Brunswick Street)

(adapted from an email from Michael Motion, Senior Project Manager, Infrastructure, Leith Programme Project Team, sent at 11:01 on 2017_10_02)

Proposed works w/c 2nd October 2017

 Road closures

  • Albert Street (planned re-opening date Tuesday 10th October)
  • Brunswick Road (will remain closed until completion of the project at the end of October)
  • McDonald Road (will remain closed until completion of the project at the end of October)
  • Brunswick Street (planned re-opening date Wednesday 18th October 2017)

Continue reading

Leith Programme Stakeholder Update 111 – Phase 4 (Iona Street to Brunswick Street)

(adapted from an email sent by Michael Motion, Senior Project Manager, Infrastructure, Turner & Townsend at 17:08 on 2017_09_22)

Completion of the road surfacing works will be noticeable as we complete areas and move the major worksites southwards towards McDonald Road and Brunswick Street. With that being the case, we will now be closing both McDonald Road and Brunswick Street junctions on Wednesday morning, 27th September with local diversions put in place. This will coincide with the opening up of both Iona Street and Albert Street. McDonald Road and Brunswick Street will remain closed until completion of all works by the end of October, as will Brunswick Road where the site compound is located. Continue reading

Leith Programme Stakeholder Update 110 – Phase 4 (Iona Street to Brunswick Street)

(adapted from an email from Michael Motion,  Senior Project Manager, Infrastructure, Turner & Townsend, sent at 11:31 on 2017_09_17)

Proposed works and worksite locations for w/c 18th September

  • Kerb realignment has been completed at the Iona Street junction, and the footpath slabbing works will progress this week
  • Completion of the footpath slabbing to the S/E corner of the Brunswick Street junction will continue this week
  • Continuing the Scottish Water works at Croall Place, followed by the footpath reinstatement works
  • Albert Street will close today for 2 weeks to accommodate the Leith Walk road re-surfacing works with associated traffic management and local diversions in place to accommodate these works
  • Road surfacing works are continuing north to south on Leith Walk, are progressing well, and will be focussed on the East side going past Albert Street this week

Continue reading

Leith Programme Stakeholder Update 109: Phase 4 (Iona Street to Brunswick Street)

(adapted from an email sent by Michael Motion of Turner & Townsend at 14:51 on 8 September. )

Dear Stakeholder

Our contractor, Crummock, returned to site as of Monday 4th September to remobilise for the completion of the Phase 4 scope of works. At that time, Brunswick Road was closed to accommodate the site compound, and will remain so until the works are completed. Iona Street was also closed to allow commencement of works to realign the kerb line, commence the road surfacing works including the raised table construction and to complete the pavement slabbing. It is likely this will take up to 3 weeks to complete, during which time Iona Street will remain closed.

In addition to the above, we are also working in the following areas:

  • Brunswick Street junction to complete the remain footpath slabbing to the S/E corner
  • Croall Place to complete the remaining Scottish Water rectification works, and to resolve surface water drainage issues
  • 2 nr road crossings on Leith Walk, north and south of Albert Street.

Continue reading

Leith Programme Stakeholder Update 107: Phase 4 (Iona Street to Brunswick Street)

 (adapted from an email from Michael Motion, Senior Project Manager at Turner & Townsend, sent at 16:51 on 21 August 2017)

As of Monday 4th September, following the Edinburgh festival embargo, our Contractor, Crummock, will be returning to Leith Walk to complete Phase 4 of the Leith Programme.  We anticipate completing these works by Friday 3rd November (being an 8 week construction programme).  Continue reading