Leith Programme Stakeholder Update 109: Phase 4 (Iona Street to Brunswick Street)

(adapted from an email sent by Michael Motion of Turner & Townsend at 14:51 on 8 September. )

Dear Stakeholder

Our contractor, Crummock, returned to site as of Monday 4th September to remobilise for the completion of the Phase 4 scope of works. At that time, Brunswick Road was closed to accommodate the site compound, and will remain so until the works are completed. Iona Street was also closed to allow commencement of works to realign the kerb line, commence the road surfacing works including the raised table construction and to complete the pavement slabbing. It is likely this will take up to 3 weeks to complete, during which time Iona Street will remain closed.

In addition to the above, we are also working in the following areas:

  • Brunswick Street junction to complete the remain footpath slabbing to the S/E corner
  • Croall Place to complete the remaining Scottish Water rectification works, and to resolve surface water drainage issues
  • 2 nr road crossings on Leith Walk, north and south of Albert Street.

Continue reading

Leith Programme Stakeholder Update 107: Phase 4 (Iona Street to Brunswick Street)

 (adapted from an email from Michael Motion, Senior Project Manager at Turner & Townsend, sent at 16:51 on 21 August 2017)

As of Monday 4th September, following the Edinburgh festival embargo, our Contractor, Crummock, will be returning to Leith Walk to complete Phase 4 of the Leith Programme.  We anticipate completing these works by Friday 3rd November (being an 8 week construction programme).  Continue reading

Leith Programme Stakeholder Update 106: Phase 4 (Pilrig Street to McDonald Road)

(adapted from an email sent by Michael Motion of Turner & Townsend at 18:00 on 8 August. We apologise for the late posting of this news: our web-weaver was on holiday.)

Dear Stakeholder,

Leith Programme Phase 4 is currently observing the Edinburgh Festival embargo on road works within the city and, as such, has now demobilised fully from Leith Walk and Iona Street.  The Contractor will return to site to re-mobilise and commence the remaining works as of Monday 28thAugust.  Continue reading